Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (400 sq ft)
$2,900 – $6,950
Per sq ft
$7.10 – $16.50
before permit
Versus US midpoint
−12%
US $5,600
Rank of 300 metros
#270
1 = most expensive

If you want to pour stamped concrete in Lubbock, plan on $2,900 to $6,950 for 400 sq ft, all in. Per sq ft, that is $7.10 to $16.50 for materials and labor, with the permit on top. The local midpoint runs 12% lower than the national one. Cement masons and concrete finishers earn a median of $23.03 an hour in the Lubbock area, 16% below the US median of $27.41.

Estimate your stamped concrete cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Two-tone color release and a border

Add-ons

Estimated cost for 400 sq ft in Lubbock, TX, standard level

$4,100 to $5,750

About $9.95 to $14 per sq ft before permits. Labor is about 45% of the bill.

Cost breakdown
PartLowHigh
Materials$2,200$2,850
Labor$1,800$2,650
Permits and fees$130$240
Total$4,100$5,750
Save and get a PDF report

Cost breakdown for 400 sq ft in Lubbock, TX

Part of the jobLowMidpointHighShare
Materials$1,700$2,550$3,40051%
Labor$1,150$2,200$3,25045%
Permits and fees$45$180$3204%
Total$2,900$4,900$6,950100%

Where the Lubbock price comes from

We price the labor side from BLS wage data for 3 trades: cement masons and concrete finishers at 60%, construction laborers at 30%, operating engineers and other construction equipment operators at 10%. Weighted together, Lubbock wages are 0.82 times the national level. Labor makes up about 45% of the midpoint estimate (48% at national prices).

On the materials line, the BEA goods price index for the Lubbock metro is 93.8 (US = 100). The midpoint materials bill for 400 sq ft comes to $2,550, compared with $2,700 at national prices. Permit and inspection fees are scaled by the broader index (91.3) and land at $45 to $320.

Is Lubbock cheap or dear? The local comparison

Same job, same size (400 sq ft), priced for the nearest metros. Midland is the priciest of the group at $5,000. El Paso is the cheapest at $4,700.

Comparison with nearby areas
AreaRangeMidpointvs. here
Lubbock, TXthis page$2,900 – $6,950$4,900
Midland, TX95 miles$2,900 – $7,100$5,000+2%
Odessa, TX115 miles$2,900 – $7,050$5,000+1%
Amarillo, TX125 miles$2,850 – $6,900$4,900−1%
Abilene, TX145 miles$2,850 – $6,950$4,900level
El Paso, TX250 miles$2,800 – $6,650$4,700−4%
Texas (statewide)$3,000 – $7,250$5,100+4%
United States$3,250 – $7,950$5,600+14%

Across 300 US metros, Lubbock comes in at #270 from the top. The priciest is Kahului, HI at $8,150; the cheapest is McAllen, TX at $4,550 (midpoints, 400 sq ft). Statewide, Lubbock is 4% below the Texas figure.

Other Texas metros

Texas metros compared with Lubbock
MetroSizeRangeMidpointvs. here
Dallas, TX4,049,800 jobs$3,150 – $7,600$5,350+9%
Houston, TX3,289,720 jobs$3,050 – $7,300$5,200+5%
Austin, TX1,293,690 jobs$3,000 – $7,250$5,100+4%
San Antonio, TX1,126,880 jobs$2,900 – $7,000$4,950+1%
El Paso, TX339,120 jobs$2,800 – $6,650$4,700−4%
McAllen, TX296,700 jobs$2,700 – $6,450$4,550−7%

Cities with a workforce like Lubbock's

Big cities and small ones price differently, so here is Lubbock against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
Atlantic City, NJ168,700 jobs$3,450 – $8,550$6,000+22%
Peoria, IL166,020 jobs$3,550 – $8,950$6,250+27%
Fort Collins, CO169,430 jobs$3,200 – $7,950$5,600+13%
Montgomery, AL165,550 jobs$2,850 – $6,900$4,850−1%

What nearby projects cost in Lubbock

Because every project leans on different trades, Lubbock's wage level does not move all prices equally. Against the US midpoint, asphalt driveway runs −11% and concrete driveway −15%.

Related projects with local prices
ProjectSizeRangevs. US
Concrete patio300 sq ft$1,100 – $3,450−13%
Concrete driveway600 sq ft$3,150 – $7,750−15%
Paver patio300 sq ft$2,600 – $4,650−14%
Concrete slab400 sq ft$2,150 – $4,600−12%
Asphalt driveway600 sq ft$2,750 – $6,550−11%
Gravel driveway1,000 sq ft$2,150 – $8,750−14%

Climate in Lubbock: timing your stamped concrete job

We use NOAA's 1991-2020 climate normals for Lubbock Wfo (5 miles from the city center). These are 30-year monthly averages, not forecasts.

April through May and September through October are the stretches where pouring concrete runs into the fewest weather problems in Lubbock (4 of 12 months). January, February, March, November and December have an average overnight low of 40°F or below; June, July and August have an average daytime high of 90°F or more.

The 40°F line is a deliberately cautious stand-in. The American Concrete Institute's cold-weather guide (ACI 306R-16) defines cold-weather concreting around an average daily air temperature below 40°F, which is colder than our test of an average overnight low at or below 40°F, so we flag a few extra shoulder months. In cold weather crews may need heated enclosures, insulating blankets or accelerated mixes, and those measures can raise a quote.

Heat matters for concrete as well. With average highs of 90°F or more in June, July and August, crews often start early, wet the base and plan for faster set times.

Lubbock gets about 19 inches of precipitation in a normal year. The wettest months are May, June and September (2.7 inches in June). Inside the workable window, April and October are the driest, at 1.4 and 1.7 inches. The station averages about 91 days a year at 90°F or above.

Does the season change the price? Probably, but we do not have a sourced seasonal price curve, so the estimator shows a year-round figure and does not adjust by month. When you collect quotes, ask whether scheduling in a slower month gets a better rate.

Monthly normals, Lubbock Wfo (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan55300.7Cold
Feb59320.6Cold
Mar68391.2Cold
Apr76481.4Workable
May84572.6Workable
Jun91662.7Hot
Jul93702.2Hot
Aug91692.0Hot
Sep84612.6Workable
Oct76501.7Workable
Nov64380.8Cold
Dec55300.8Cold

Cost by quality level and size in Lubbock

Three bands are cut from the same cited range and localized for Lubbock wages and prices. They overlap on purpose: a good standard job and a modest premium job can cost the same. The grid below prices the same bands at 3 common sizes.

Basic

$2,900 to $4,500

Basic pattern, one integral color

Standard

$4,100 to $5,750

Two-tone color release and a border

Premium

$5,350 to $6,950

Multi-color, hand-detailed, sealed to a high finish

Cost by size and quality level
SizeBasicStandardPremium
10x20 patio (200 sq ft)$1,450 – $2,350$2,100 – $3,000$2,750 – $3,650
20x20 patio (400 sq ft)$2,900 – $4,500$4,100 – $5,750$5,350 – $6,950
2-car driveway (600 sq ft)$4,300 – $6,700$6,100 – $8,500$7,900 – $10,300

Stamped concrete: what moves the price in Lubbock

  • Pattern and color

    Basic to average coloring runs $8-$19 per sq ft. A 2-car stamped driveway runs $12-$18 per sq ft (HomeGuide); Estimators.us puts decorative slabs at $15-$30.

  • Specialist labor

    Stamping has to be done before the concrete sets, so crews arrive in larger teams and charge for it.

  • Sealing and vapor barrier

    Sealer is usually quoted separately; vapor barrier material is $0.20-$1.50 per sq ft depending on thickness (HomeGuide).

Lubbock labor market for stamped concrete

Wages are the part of this estimate that changes most from town to town. 3 trades carry the job here, and each is compared with its US median. The weighted result for Lubbock is 0.82 times the national level.

For cement masons and concrete finishers (47-2051, weighted 60%) the local median is $23.03 an hour, which is 16% below the national $27.41. The middle half of them earn between $18.75 and $23.45 an hour. BLS counts 150 of them working in the area, 9.0 for every 10,000 jobs (US: 13.3), so the local bench is thinner than average.

Construction laborers (47-2061), 30% of the weighting: a median of $17.78 an hour, 22% below the US median of $22.66. The middle half of them earn between $16.45 and $21.13 an hour. About 980 work in the metro. That is 58.8 per 10,000 jobs, compared with 70.5 nationally, so expect fewer local crews to bid.

For operating engineers and other construction equipment operators (47-2073, weighted 10%) the local median is $22.35 an hour, which is 22% below the national $28.78. The middle half of them earn between $21.37 and $27.40 an hour. BLS counts 550 of them working in the area, 33.0 for every 10,000 jobs (US: 30.7), so the local bench is about average.

Quotes come from real crews, not medians. If the cement masons and concrete finishers on your job are paid at the 75th percentile ($23.45 an hour) instead of the median, the labor line grows by about $25. At the 25th percentile ($18.75) it shrinks by about $250. The total moves by 0.5% or 5.1%, so wages alone rarely explain a quote that is far outside our range.

For context on the local economy, BLS counts 166,780 jobs in the Lubbock area. That makes it the 140th largest of the 300 metros we cover, with 0.11% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)60%$18.75$23.03$23.45$27.410.84metro
Construction laborers (47-2061)30%$16.45$17.78$21.13$22.660.78metro
Operating engineers and other construction equipment operators (47-2073)10%$21.37$22.35$27.40$28.780.78metro
Blended100%0.82

Add-ons priced for Lubbock

Extras are quoted nationally and then scaled to Lubbock by the average of the local wage index (0.82) and goods index (0.94), a factor of 0.88. Tick any of them in the estimator above to add them to your total. Treat these as planning figures: an add-on touches different trades than the main job, so the scaling is an approximation.

Add-on prices
Add-onLocal range
Add a vapor barrier$180 – $350

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $4,100 to $5,750 for Lubbock, TX is attached.

Detailed stamped concrete report for Lubbock, TX, $9

The report lays out the stamped concrete numbers for Lubbock, TX line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Stamped concrete in Lubbock: your questions

+How much does it cost to pour stamped concrete in Lubbock?

For 400 sq ft, expect $2,900 to $6,950 in the Lubbock area. A standard-spec job lands at $4,100 to $5,750. Small jobs usually cost more per sq ft and large ones less.

+What is the price per sq ft for stamped concrete in Lubbock?

About $7.10 to $16.50 per sq ft for materials and labor, plus $45 to $320 for the permit if one is needed. The US range is $8 to $19.

+Is stamped concrete cheaper in Lubbock or Midland?

Midland is 95 miles away. The midpoint for 400 sq ft there is $5,000, which is 2% more than Lubbock ($4,900). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Lubbock?

About 45% at the midpoint, or $2,200 out of $4,900. Materials are 51% and permits 4%. Nationally, labor is 48%.

+What would 20x20 patio (400 sq ft) cost in Lubbock?

$2,900 to $6,950. Pick a different size in the estimator above to get your own number.

+Does stamped concrete need a permit in Lubbock?

Often, but rules are set by your city or county building office, so call before you hire. Budget $45 to $320 for fees in the Lubbock area (our national range of $50 to $350 scaled by the local price level).

+Is Lubbock expensive for stamped concrete compared with the rest of Texas?

Lubbock is 4% below the Texas statewide estimate ($5,100 at the midpoint). We cover 21 metros in Texas; see the state page to compare them.

+What do cement masons and concrete finishers earn in Lubbock?

The BLS median is $23.03 an hour in the Lubbock area, compared with $27.41 nationally. The 25th to 75th percentile range is $18.75 to $23.45.

+What do basic and premium stamped concrete work cost in Lubbock?

For 400 sq ft, basic work runs $2,900 to $4,500 and premium work $5,350 to $6,950. Basic means: basic pattern, one integral color. Premium means: multi-color, hand-detailed, sealed to a high finish.

+When is the best time to pour stamped concrete in Lubbock?

Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are April through May and September through October. April and October are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.

+What does "add a vapor barrier" add in Lubbock?

$180 to $350 for 400 sq ft, from a national range scaled by the local wage and goods indexes.

Stamped concrete near Lubbock

Stamped concrete: all pricesStamped concrete in TexasAll projects in LubbockTexas cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = SimplyWise's 200 sq ft stamped-patio line ($900-$1,800), divided by 200 sq ft.