Stamped concrete cost in Orlando, FL
Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.
- Typical range (400 sq ft)
- $2,950 – $7,200
- Per sq ft
- $7.30 – $17
- before permit
- Versus US midpoint
- −9%
- US $5,600
- Rank of 300 metros
- #227
- 1 = most expensive
Local price for stamped concrete in the Orlando area: $2,950 to $7,200 for 400 sq ft. The low end is a basic job on easy ground; the high end is a premium spec with harder access. The midpoint runs 9% lower than the US figure. Cement masons and concrete finishers earn a median of $22.98 an hour in the Orlando area, 16% below the US median of $27.41.
Estimate your stamped concrete cost
Pick a size, a quality level and where you live. Prices update as you type.
Estimated cost for 400 sq ft in Orlando, FL, standard level
$4,250 to $5,950
About $10.50 to $14 per sq ft before permits. Labor is about 45% of the bill.
| Part | Low | High |
|---|---|---|
| Materials | $2,250 | $2,950 |
| Labor | $1,850 | $2,750 |
| Permits and fees | $140 | $260 |
| Total | $4,250 | $5,950 |
Cost breakdown for 400 sq ft in Orlando, FL
| Part of the job | Low | Midpoint | High | Share |
|---|---|---|---|---|
| Materials | $1,750 | $2,600 | $3,450 | 51% |
| Labor | $1,200 | $2,300 | $3,400 | 45% |
| Permits and fees | $50 | $200 | $350 | 4% |
| Total | $2,950 | $5,100 | $7,200 | 100% |
Why Orlando prices look the way they do
The wage side of the estimate leans on cement masons and concrete finishers, who do 60% of the hours on a typical job. Their local median is $22.98 an hour. Add the other trades involved and the blended wage index for Orlando is 0.85 (US = 1.00), which puts labor at 45% of the total.
Materials are scaled with BEA's regional price parity for goods. Orlando is at 96.2 against 100 for the US, so a materials line of $2,700 nationally becomes $2,600 here (midpoint, 400 sq ft). Permits follow the all-items index of 101.4: $50 to $350.
Specs and site conditions that change a Orlando bid
Specialist labor
Stamping has to be done before the concrete sets, so crews arrive in larger teams and charge for it.
Sealing and vapor barrier
Sealer is usually quoted separately; vapor barrier material is $0.20-$1.50 per sq ft depending on thickness (HomeGuide).
Not included
These prices don't include site prep that depends on the project: demolition, grading, or a thicker base.
Is Orlando cheap or dear? The local comparison
Of the five closest metros, 2 are cheaper than Orlando. Ocala is the lowest at about $5,000 (midpoint, 400 sq ft), 65 miles away.
| Area | Range | Midpoint | vs. here |
|---|---|---|---|
| Orlando, FLthis page | $2,950 – $7,200 | $5,100 | |
| Lakeland, FL40 miles | $2,950 – $7,150 | $5,050 | −1% |
| Palm Bay, FL40 miles | $3,000 – $7,300 | $5,150 | +1% |
| Deltona, FL50 miles | $3,000 – $7,250 | $5,100 | +1% |
| Ocala, FL65 miles | $2,900 – $7,050 | $5,000 | −2% |
| Sebastian, FL70 miles | $3,000 – $7,300 | $5,150 | +1% |
| Florida (statewide) | $3,050 – $7,400 | $5,200 | +2% |
| United States | $3,250 – $7,950 | $5,600 | +10% |
Out of the 300 metros we cover, Orlando ranks #227 for the cost of this job (#1 is the most expensive). Statewide, Orlando is 2% below the Florida figure.
Elsewhere in Florida
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Miami, FL | 2,819,940 jobs | $3,150 – $7,700 | $5,450 | +7% |
| Tampa, FL | 1,447,120 jobs | $3,000 – $7,350 | $5,150 | +1% |
| Jacksonville, FL | 765,930 jobs | $3,000 – $7,300 | $5,150 | +1% |
| North Port, FL | 339,940 jobs | $3,050 – $7,400 | $5,200 | +2% |
| Cape Coral, FL | 304,790 jobs | $3,000 – $7,300 | $5,150 | +1% |
| Lakeland, FL | 265,280 jobs | $2,950 – $7,150 | $5,050 | −1% |
Metros of a similar size
Big cities and small ones price differently, so here is Orlando against the 4 metros with the closest total employment.
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Tampa, FL | 1,447,120 jobs | $3,000 – $7,350 | $5,150 | +1% |
| Charlotte, NC | 1,358,370 jobs | $3,000 – $7,350 | $5,200 | +2% |
| San Diego, CA | 1,538,060 jobs | $3,700 – $9,100 | $6,400 | +25% |
| Baltimore, MD | 1,356,680 jobs | $3,200 – $7,850 | $5,500 | +8% |
The best months for stamped concrete in Orlando
Climate numbers on this page come from NOAA's 1991-2020 U.S. Climate Normals at the nearest suitable station, Orlando Intl Ap (5 miles from the city center). They are 30-year averages, so any one year can run hotter, colder or wetter.
For pouring concrete, the comfortable months in Orlando are October through May: 8 of 12. Outside them, June, July, August and September have an average daytime high of 90°F or more.
Heat matters for concrete as well. With average highs of 90°F or more in June, July, August and September, crews often start early, wet the base and plan for faster set times.
Orlando gets about 51 inches of precipitation in a normal year. The wettest months are June, July and August (8.1 inches in June). Inside the workable window, February and November are the driest, at 2.0 and 1.8 inches. The station averages about 110 days a year at 90°F or above.
We do not adjust the estimate by month, because we have no reliable published data on seasonal pricing. It is still worth asking contractors whether an off-peak start date changes their bid.
| Month | Avg high °F | Avg low °F | Precip (in) | For this job |
|---|---|---|---|---|
| Jan | 72 | 50 | 2.5 | Workable |
| Feb | 75 | 52 | 2.0 | Workable |
| Mar | 79 | 56 | 3.0 | Workable |
| Apr | 84 | 61 | 2.6 | Workable |
| May | 88 | 66 | 4.0 | Workable |
| Jun | 91 | 72 | 8.1 | Hot |
| Jul | 92 | 73 | 7.5 | Hot |
| Aug | 92 | 74 | 7.7 | Hot |
| Sep | 90 | 72 | 6.4 | Hot |
| Oct | 85 | 66 | 3.5 | Workable |
| Nov | 78 | 58 | 1.8 | Workable |
| Dec | 74 | 53 | 2.5 | Workable |
What nearby projects cost in Orlando
Jobs that often go together with stamped concrete are priced below at their usual sizes, using the same Orlando wage and price inputs. Compared with national midpoints, asphalt driveway comes out highest (−7%) and concrete driveway lowest (−12%); the gap comes from the trades each job uses.
| Project | Size | Range | vs. US |
|---|---|---|---|
| Concrete patio | 300 sq ft | $1,150 – $3,600 | −9% |
| Concrete driveway | 600 sq ft | $3,250 – $8,100 | −12% |
| Paver patio | 300 sq ft | $2,700 – $4,950 | −10% |
| Concrete slab | 400 sq ft | $2,200 – $4,800 | −8% |
| Asphalt driveway | 600 sq ft | $2,850 – $6,850 | −7% |
| Gravel driveway | 1,000 sq ft | $2,250 – $9,300 | −9% |
Add-ons priced for Orlando
Add-ons start from national price ranges and are scaled by 0.91 for Orlando, which is the average of the area's wage index (0.85) and goods price index (0.96). The estimator above can add them to your total.
| Add-on | Local range |
|---|---|
| Add a vapor barrier | $180 – $360 |
Who does the work: Orlando trade wages
The labor line is built from BLS wage data, one trade at a time. This job draws on 3 trades. We compare each trade's local median with the US median, weight the ratios by how much of the job each trade does, and apply the blend to the national labor cost. For Orlando the blend is 0.85.
Cement masons and concrete finishers (47-2051), 60% of the weighting: a median of $22.98 an hour, 16% below the US median of $27.41. The middle half of them earn between $21.09 and $27.33 an hour. About 2,120 work in the metro. That is 15.0 per 10,000 jobs, compared with 13.3 nationally, so the supply of crews looks typical.
For construction laborers (47-2061, weighted 30%) the local median is $19.66 an hour, which is 13% below the national $22.66. The middle half of them earn between $17.62 and $22.55 an hour. BLS counts 12,290 of them working in the area, 87.1 for every 10,000 jobs (US: 70.5), so the local bench is deeper than average.
Operating engineers and other construction equipment operators (47-2073), 10% of the weighting: a median of $24.53 an hour, 15% below the US median of $28.78. The middle half of them earn between $22.61 and $27.47 an hour. About 4,330 work in the metro. That is 30.7 per 10,000 jobs, compared with 30.7 nationally, so the supply of crews looks typical.
A quick sensitivity check: moving the lead trade (cement masons and concrete finishers) from the median to the 75th percentile wage adds about $260 to the midpoint estimate; the 25th percentile takes off about $110. That is a swing of roughly 2.2% to 5.0% of the total, which is useful for judging whether a bid reflects wages or something else, such as scope or margin.
Orlando-Kissimmee-Sanford has 1,411,730 jobs in total (BLS, May 2025), ranking 20th by size among the 300 metros on this site.
| Trade | Weight | 25th pct | Median | 75th pct | US median | Ratio | Level used |
|---|---|---|---|---|---|---|---|
| Cement masons and concrete finishers (47-2051) | 60% | $21.09 | $22.98 | $27.33 | $27.41 | 0.84 | metro |
| Construction laborers (47-2061) | 30% | $17.62 | $19.66 | $22.55 | $22.66 | 0.87 | metro |
| Operating engineers and other construction equipment operators (47-2073) | 10% | $22.61 | $24.53 | $27.47 | $28.78 | 0.85 | metro |
| Blended | 100% | 0.85 | |||||
Pick a size, pick a tier: stamped concrete pricing in Orlando
The cited range is split into basic, standard and premium bands, then scaled to Orlando. Bands overlap, because plenty of standard jobs cost as much as a light premium one. Sizes run from 10x20 patio (200 sq ft) to 2-car driveway (600 sq ft).
Basic
$2,950 to $4,650
Basic pattern, one integral color
Standard
$4,250 to $5,950
Two-tone color release and a border
Premium
$5,500 to $7,200
Multi-color, hand-detailed, sealed to a high finish
| Size | Basic | Standard | Premium |
|---|---|---|---|
| 10x20 patio (200 sq ft) | $1,500 – $2,400 | $2,200 – $3,100 | $2,850 – $3,800 |
| 20x20 patio (400 sq ft) | $2,950 – $4,650 | $4,250 – $5,950 | $5,500 – $7,200 |
| 2-car driveway (600 sq ft) | $4,450 – $6,900 | $6,300 – $8,800 | $8,150 – $10,600 |
Get 3 local quotes
Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $4,250 to $5,950 for Orlando, FL is attached.
Detailed stamped concrete report for Orlando, FL, $9
The report lays out the stamped concrete numbers for Orlando, FL line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.
Stamped concrete in Orlando: your questions
+How much does it cost to pour stamped concrete in Orlando?
For 400 sq ft, expect $2,950 to $7,200 in the Orlando area. A standard-spec job lands at $4,250 to $5,950. Small jobs usually cost more per sq ft and large ones less.
+What is the price per sq ft for stamped concrete in Orlando?
About $7.30 to $17 per sq ft for materials and labor, plus $50 to $350 for the permit if one is needed. The US range is $8 to $19.
+Is stamped concrete cheaper in Orlando or Lakeland?
Lakeland is 40 miles away. The midpoint for 400 sq ft there is $5,050, which is 1% less than Orlando ($5,100). Wage and materials indexes both feed that gap.
+How much of the bill is labor in Orlando?
About 45% at the midpoint, or $2,300 out of $5,100. Materials are 51% and permits 4%. Nationally, labor is 48%.
+What would 20x20 patio (400 sq ft) cost in Orlando?
$2,950 to $7,200. Pick a different size in the estimator above to get your own number.
+Does stamped concrete need a permit in Orlando?
Often, but rules are set by your city or county building office, so call before you hire. Budget $50 to $350 for fees in the Orlando area (our national range of $50 to $350 scaled by the local price level).
+Is Orlando expensive for stamped concrete compared with the rest of Florida?
Orlando is 2% below the Florida statewide estimate ($5,200 at the midpoint). We cover 19 metros in Florida; see the state page to compare them.
+What do cement masons and concrete finishers earn in Orlando?
The BLS median is $22.98 an hour in the Orlando area, compared with $27.41 nationally. The 25th to 75th percentile range is $21.09 to $27.33.
+What do basic and premium stamped concrete work cost in Orlando?
For 400 sq ft, basic work runs $2,950 to $4,650 and premium work $5,500 to $7,200. Basic means: basic pattern, one integral color. Premium means: multi-color, hand-detailed, sealed to a high finish.
+When is the best time to pour stamped concrete in Orlando?
Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are October through May. February and November are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.
+What does "add a vapor barrier" add in Orlando?
$180 to $360 for 400 sq ft, from a national range scaled by the local wage and goods indexes.
Stamped concrete near Orlando
Where these numbers come from
Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.
- HomeGuide: How Much Does Stamped Concrete Cost? (2026) (accessed November 4, 2026)
- SimplyWise: Concrete Estimate Template: Free PDF + Excel (2026) (accessed November 4, 2026)
- BLS Occupational Employment and Wage Statistics, May 2025
- BEA Regional Price Parities, 2024
- NOAA NCEI U.S. Climate Normals, 1991-2020
Note on derived figures: Materials = SimplyWise's 200 sq ft stamped-patio line ($900-$1,800), divided by 200 sq ft.