Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (400 sq ft)
$3,000 – $7,350
Per sq ft
$7.40 – $17.50
before permit
Versus US midpoint
−8%
US $5,600
Rank of 300 metros
#201
1 = most expensive

Local price for stamped concrete in the Tampa area: $3,000 to $7,350 for 400 sq ft. The low end is a basic job on easy ground; the high end is a premium spec with harder access. The midpoint runs 8% lower than the US figure. Cement masons and concrete finishers earn a median of $23.84 an hour in the Tampa area, 13% below the US median of $27.41.

Estimate your stamped concrete cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Two-tone color release and a border

Add-ons

Estimated cost for 400 sq ft in Tampa, FL, standard level

$4,300 to $6,050

About $10.50 to $14.50 per sq ft before permits. Labor is about 46% of the bill.

Cost breakdown
PartLowHigh
Materials$2,250$2,900
Labor$1,950$2,850
Permits and fees$140$260
Total$4,300$6,050
Save and get a PDF report

Cost breakdown for 400 sq ft in Tampa, FL

Part of the jobLowMidpointHighShare
Materials$1,700$2,600$3,45050%
Labor$1,250$2,400$3,55046%
Permits and fees$50$200$3504%
Total$3,000$5,150$7,350100%

Why Tampa prices look the way they do

Labor is 46% of the midpoint bill here, against 48% nationally. The mix of trades behind this job is cement masons and concrete finishers (60%), construction laborers (30%), operating engineers and other construction equipment operators (10%). We weight each trade's local median wage by that share and compare it with the national median. In Tampa the blended ratio comes out at 0.88.

Materials are scaled with BEA's regional price parity for goods. Tampa is at 95.5 against 100 for the US, so a materials line of $2,700 nationally becomes $2,600 here (midpoint, 400 sq ft). Permits follow the all-items index of 100.9: $50 to $350.

The best months for stamped concrete in Tampa

Climate numbers on this page come from NOAA's 1991-2020 U.S. Climate Normals at the nearest suitable station, Tampa Intl Ap (5 miles from the city center). They are 30-year averages, so any one year can run hotter, colder or wetter.

For pouring concrete, the comfortable months in Tampa are October through May: 8 of 12. Outside them, June, July, August and September have an average daytime high of 90°F or more.

Heat matters for concrete as well. With average highs of 90°F or more in June, July, August and September, crews often start early, wet the base and plan for faster set times.

Tampa gets about 49 inches of precipitation in a normal year. The wettest months are June, July and August (9.0 inches in August). Inside the workable window, October and November are the driest, at 2.3 and 1.4 inches. The station averages about 94 days a year at 90°F or above.

We do not adjust the estimate by month, because we have no reliable published data on seasonal pricing. It is still worth asking contractors whether an off-peak start date changes their bid.

Monthly normals, Tampa Intl Ap (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan71532.6Workable
Feb74562.6Workable
Mar78592.5Workable
Apr83652.5Workable
May88712.6Workable
Jun91757.4Hot
Jul91777.8Hot
Aug91779.0Hot
Sep90756.1Hot
Oct86692.3Workable
Nov79611.4Workable
Dec74562.6Workable

Why two Tampa quotes can differ

  • Specialist labor

    Stamping has to be done before the concrete sets, so crews arrive in larger teams and charge for it.

  • Sealing and vapor barrier

    Sealer is usually quoted separately; vapor barrier material is $0.20-$1.50 per sq ft depending on thickness (HomeGuide).

  • Not included

    These prices don't include site prep that depends on the project: demolition, grading, or a thicker base.

Related projects, priced for Tampa

Jobs that often go together with stamped concrete are priced below at their usual sizes, using the same Tampa wage and price inputs. Compared with national midpoints, paver patio comes out highest (−6%) and concrete driveway lowest (−9%); the gap comes from the trades each job uses.

Related projects with local prices
ProjectSizeRangevs. US
Concrete patio300 sq ft$1,150 – $3,700−8%
Concrete driveway600 sq ft$3,350 – $8,300−9%
Paver patio300 sq ft$2,800 – $5,150−6%
Concrete slab400 sq ft$2,250 – $4,850−7%
Asphalt driveway600 sq ft$2,850 – $6,850−7%
Gravel driveway1,000 sq ft$2,300 – $9,400−8%

Tampa: what basic, standard and premium work costs

The cited range is split into basic, standard and premium bands, then scaled to Tampa. Bands overlap, because plenty of standard jobs cost as much as a light premium one. Sizes run from 10x20 patio (200 sq ft) to 2-car driveway (600 sq ft).

Basic

$3,000 to $4,750

Basic pattern, one integral color

Standard

$4,300 to $6,050

Two-tone color release and a border

Premium

$5,600 to $7,350

Multi-color, hand-detailed, sealed to a high finish

Cost by size and quality level
SizeBasicStandardPremium
10x20 patio (200 sq ft)$1,550 – $2,450$2,200 – $3,150$2,900 – $3,850
20x20 patio (400 sq ft)$3,000 – $4,750$4,300 – $6,050$5,600 – $7,350
2-car driveway (600 sq ft)$4,500 – $7,000$6,400 – $8,900$8,300 – $10,800

Who does the work: Tampa trade wages

The labor line is built from BLS wage data, one trade at a time. This job draws on 3 trades. We compare each trade's local median with the US median, weight the ratios by how much of the job each trade does, and apply the blend to the national labor cost. For Tampa the blend is 0.88.

Cement masons and concrete finishers (47-2051), 60% of the weighting: a median of $23.84 an hour, 13% below the US median of $27.41. The middle half of them earn between $22.01 and $28.88 an hour. About 1,780 work in the metro. That is 12.3 per 10,000 jobs, compared with 13.3 nationally, so the supply of crews looks typical.

For construction laborers (47-2061, weighted 30%) the local median is $21.04 an hour, which is 7% below the national $22.66. The middle half of them earn between $17.87 and $22.81 an hour. BLS counts 12,860 of them working in the area, 88.9 for every 10,000 jobs (US: 70.5), so the local bench is deeper than average.

Operating engineers and other construction equipment operators (47-2073), 10% of the weighting: a median of $24.18 an hour, 16% below the US median of $28.78. The middle half of them earn between $22.69 and $28.27 an hour. About 3,980 work in the metro. That is 27.5 per 10,000 jobs, compared with 30.7 nationally, so the supply of crews looks typical.

A quick sensitivity check: moving the lead trade (cement masons and concrete finishers) from the median to the 75th percentile wage adds about $300 to the midpoint estimate; the 25th percentile takes off about $110. That is a swing of roughly 2.1% to 5.8% of the total, which is useful for judging whether a bid reflects wages or something else, such as scope or margin.

Tampa-St. Petersburg-Clearwater has 1,447,120 jobs in total (BLS, May 2025), ranking 19th by size among the 300 metros on this site.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)60%$22.01$23.84$28.88$27.410.87metro
Construction laborers (47-2061)30%$17.87$21.04$22.81$22.660.93metro
Operating engineers and other construction equipment operators (47-2073)10%$22.69$24.18$28.27$28.780.84metro
Blended100%0.88

Optional extras in Tampa

Add-ons start from national price ranges and are scaled by 0.92 for Tampa, which is the average of the area's wage index (0.88) and goods price index (0.95). The estimator above can add them to your total.

Add-on prices
Add-onLocal range
Add a vapor barrier$180 – $370

Tampa against nearby metros and the rest of Florida

Of the five closest metros, 4 are cheaper than Tampa. Ocala is the lowest at about $5,000 (midpoint, 400 sq ft), 80 miles away.

Comparison with nearby areas
AreaRangeMidpointvs. here
Tampa, FLthis page$3,000 – $7,350$5,150
Lakeland, FL50 miles$2,950 – $7,150$5,050−3%
North Port, FL55 miles$3,050 – $7,400$5,200+1%
Orlando, FL75 miles$2,950 – $7,200$5,100−1%
Ocala, FL80 miles$2,900 – $7,050$5,000−3%
Punta Gorda, FL90 miles$3,000 – $7,300$5,150level
Florida (statewide)$3,050 – $7,400$5,200+1%
United States$3,250 – $7,950$5,600+8%

Out of the 300 metros we cover, Tampa ranks #201 for the cost of this job (#1 is the most expensive). Statewide, Tampa is 1% below the Florida figure.

Elsewhere in Florida

Florida metros compared with Tampa
MetroSizeRangeMidpointvs. here
Miami, FL2,819,940 jobs$3,150 – $7,700$5,450+5%
Orlando, FL1,411,730 jobs$2,950 – $7,200$5,100−1%
Jacksonville, FL765,930 jobs$3,000 – $7,300$5,150level
North Port, FL339,940 jobs$3,050 – $7,400$5,200+1%
Cape Coral, FL304,790 jobs$3,000 – $7,300$5,150level
Lakeland, FL265,280 jobs$2,950 – $7,150$5,050−3%

Metros of a similar size

Big cities and small ones price differently, so here is Tampa against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
San Diego, CA1,538,060 jobs$3,700 – $9,100$6,400+24%
Orlando, FL1,411,730 jobs$2,950 – $7,200$5,100−1%
Denver, CO1,609,350 jobs$3,350 – $8,300$5,850+13%
Charlotte, NC1,358,370 jobs$3,000 – $7,350$5,200level

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $4,300 to $6,050 for Tampa, FL is attached.

Take this estimate with you: PDF report, $9

The report lays out the stamped concrete numbers for Tampa, FL line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Stamped concrete in Tampa: your questions

+How much does it cost to pour stamped concrete in Tampa?

For 400 sq ft, expect $3,000 to $7,350 in the Tampa area. A standard-spec job lands at $4,300 to $6,050. Small jobs usually cost more per sq ft and large ones less.

+What is the price per sq ft for stamped concrete in Tampa?

About $7.40 to $17.50 per sq ft for materials and labor, plus $50 to $350 for the permit if one is needed. The US range is $8 to $19.

+Is stamped concrete cheaper in Tampa or Lakeland?

Lakeland is 50 miles away. The midpoint for 400 sq ft there is $5,050, which is 3% less than Tampa ($5,150). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Tampa?

About 46% at the midpoint, or $2,400 out of $5,150. Materials are 50% and permits 4%. Nationally, labor is 48%.

+What would 20x20 patio (400 sq ft) cost in Tampa?

$3,000 to $7,350. Pick a different size in the estimator above to get your own number.

+Does stamped concrete need a permit in Tampa?

Often, but rules are set by your city or county building office, so call before you hire. Budget $50 to $350 for fees in the Tampa area (our national range of $50 to $350 scaled by the local price level).

+Is Tampa expensive for stamped concrete compared with the rest of Florida?

Tampa is 1% below the Florida statewide estimate ($5,200 at the midpoint). We cover 19 metros in Florida; see the state page to compare them.

+What do cement masons and concrete finishers earn in Tampa?

The BLS median is $23.84 an hour in the Tampa area, compared with $27.41 nationally. The 25th to 75th percentile range is $22.01 to $28.88.

+What do basic and premium stamped concrete work cost in Tampa?

For 400 sq ft, basic work runs $3,000 to $4,750 and premium work $5,600 to $7,350. Basic means: basic pattern, one integral color. Premium means: multi-color, hand-detailed, sealed to a high finish.

+When is the best time to pour stamped concrete in Tampa?

Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are October through May. October and November are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.

+What does "add a vapor barrier" add in Tampa?

$180 to $370 for 400 sq ft, from a national range scaled by the local wage and goods indexes.

Stamped concrete near Tampa

Stamped concrete: all pricesStamped concrete in FloridaAll projects in TampaFlorida cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = SimplyWise's 200 sq ft stamped-patio line ($900-$1,800), divided by 200 sq ft.