Retaining wall cost in Boise, ID
Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.
- Typical range (200 sq ft of wall face)
- $7,000 – $13,200
- Per sq ft of wall face
- $34.50 – $63.50
- before permit
- Versus US midpoint
- −2%
- US $10,300
- Rank of 300 metros
- #147
- 1 = most expensive
A retaining wall in Boise, ID usually costs $7,000 to $13,200 for 200 sq ft of wall face. That works out to about $34.50 to $63.50 per sq ft of wall face before permits. That is within a few percent of the national midpoint, so there is little local premium or discount. Building materials run about 4% below the US average here (BEA goods price index 96.2).
Estimate your retaining wall cost
Pick a size, a quality level and where you live. Prices update as you type.
Estimated cost for 200 sq ft of wall face in Boise, ID, standard level
$8,850 to $11,300
About $43.50 to $55 per sq ft of wall face before permits. Labor is about 47% of the bill.
| Part | Low | High |
|---|---|---|
| Materials | $4,150 | $6,050 |
| Labor | $4,550 | $4,950 |
| Permits and fees | $170 | $320 |
| Total | $8,850 | $11,300 |
Cost breakdown for 200 sq ft of wall face in Boise, ID
| Part of the job | Low | Midpoint | High | Share |
|---|---|---|---|---|
| Materials | $2,700 | $5,100 | $7,500 | 51% |
| Labor | $4,250 | $4,750 | $5,250 | 47% |
| Permits and fees | $50 | $250 | $440 | 2% |
| Total | $7,000 | $10,100 | $13,200 | 100% |
What is behind the Boise number
Labor is 47% of the midpoint bill here, against 46% nationally. The mix of trades behind this job is brickmasons and blockmasons (50%), construction laborers (30%), operating engineers and other construction equipment operators (20%). We weight each trade's local median wage by that share and compare it with the national median. In Boise the blended ratio comes out at 1.01.
Materials are scaled with BEA's regional price parity for goods. Boise is at 96.2 against 100 for the US, so a materials line of $5,300 nationally becomes $5,100 here (midpoint, 200 sq ft of wall face). Permits follow the all-items index of 98.4: $50 to $440.
Is Boise cheap or dear? The local comparison
Same job, same size (200 sq ft of wall face), priced for the nearest metros. Bend is the priciest of the group at $11,200. Logan is the cheapest at $9,900.
| Area | Range | Midpoint | vs. here |
|---|---|---|---|
| Boise, IDthis page | $7,000 – $13,200 | $10,100 | |
| Idaho Falls, ID190 miles | $7,200 – $13,400 | $10,300 | +2% |
| Logan, UT235 miles | $6,800 – $13,000 | $9,900 | −2% |
| Salt Lake City, UT235 miles | $6,950 – $13,200 | $10,000 | level |
| Bend, OR250 miles | $7,800 – $14,600 | $11,200 | +11% |
| Ogden, UT255 miles | $6,900 – $13,100 | $10,000 | −1% |
| Idaho (statewide) | $7,000 – $13,200 | $10,100 | level |
| United States | $7,050 – $13,500 | $10,300 | +2% |
Out of the 300 metros we cover, Boise ranks #147 for the cost of this job (#1 is the most expensive). Statewide, Boise is 0% above the Idaho figure.
Elsewhere in Idaho
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Idaho Falls, ID | 81,840 jobs | $7,200 – $13,400 | $10,300 | +2% |
| Coeur d'Alene, ID | 72,280 jobs | $7,100 – $13,400 | $10,200 | +2% |
Metros of a similar size
Big cities and small ones price differently, so here is Boise against the 4 metros with the closest total employment.
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Charleston, SC | 394,170 jobs | $6,250 – $12,300 | $9,300 | −8% |
| Tucson, AZ | 389,630 jobs | $6,650 – $12,800 | $9,700 | −4% |
| Columbia, SC | 394,200 jobs | $6,200 – $12,200 | $9,200 | −9% |
| Allentown, PA | 377,180 jobs | $7,200 – $13,600 | $10,400 | +3% |
Boise weather and the retaining wall calendar
Climate numbers on this page come from NOAA's 1991-2020 U.S. Climate Normals at the nearest suitable station, Boise Air Terminal (5 miles from the city center). They are 30-year averages, so any one year can run hotter, colder or wetter.
For digging, grading and setting material in the ground, the comfortable months in Boise are March through June and September through October: 6 of 12. Outside them, January, February, November and December have an average overnight low at or below freezing (32°F), and July and August have an average daytime high of 90°F or more.
In January, February, November and December the average low is at or below freezing, which means frozen ground and slower digging, compaction and sod or stone placement. NOAA counts about 108 days a year with a low at or below 32°F at this station.
Boise gets about 12 inches of precipitation in a normal year, including roughly 18 inches of snow. The wettest months are January, May and December (1.5 inches in December). Inside the workable window, June and September are the driest, at 0.8 and 0.4 inches. The station averages about 55 days a year at 90°F or above.
We do not adjust the estimate by month, because we have no reliable published data on seasonal pricing. It is still worth asking contractors whether an off-peak start date changes their bid.
| Month | Avg high °F | Avg low °F | Precip (in) | For this job |
|---|---|---|---|---|
| Jan | 39 | 26 | 1.4 | Cold |
| Feb | 46 | 29 | 1.0 | Cold |
| Mar | 56 | 35 | 1.3 | Workable |
| Apr | 62 | 40 | 1.2 | Workable |
| May | 72 | 48 | 1.4 | Workable |
| Jun | 81 | 54 | 0.8 | Workable |
| Jul | 93 | 62 | 0.2 | Hot |
| Aug | 91 | 61 | 0.2 | Hot |
| Sep | 80 | 53 | 0.4 | Workable |
| Oct | 65 | 42 | 0.8 | Workable |
| Nov | 49 | 32 | 1.2 | Cold |
| Dec | 39 | 25 | 1.5 | Cold |
What local crews earn in Boise
The labor line is built from BLS wage data, one trade at a time. This job draws on 3 trades. We compare each trade's local median with the US median, weight the ratios by how much of the job each trade does, and apply the blend to the national labor cost. For Boise the blend is 1.01.
For brickmasons and blockmasons (47-2021, weighted 50%) the local median is $30.06 an hour, which is in line with the national $29.87. The middle half of them earn between $28.30 and $37.48 an hour. BLS counts 150 of them working in the area, 3.8 for every 10,000 jobs (US: 3.4), so the local bench is about average.
For construction laborers (47-2061, weighted 30%) the local median is $22.84 an hour, which is in line with the national $22.66. The middle half of them earn between $19.98 and $25.18 an hour. BLS counts 4,700 of them working in the area, 120.0 for every 10,000 jobs (US: 70.5), so the local bench is deeper than average.
Operating engineers and other construction equipment operators (47-2073), 20% of the weighting: a median of $29.29 an hour, in line with the US median of $28.78. The middle half of them earn between $25.58 and $31.56 an hour. About 1,730 work in the metro. That is 44.2 per 10,000 jobs, compared with 30.7 nationally, which suggests plenty of local crews to bid.
A quick sensitivity check: moving the lead trade (brickmasons and blockmasons) from the median to the 75th percentile wage adds about $580 to the midpoint estimate; the 25th percentile takes off about $140. That is a swing of roughly 1.4% to 5.8% of the total, which is useful for judging whether a bid reflects wages or something else, such as scope or margin.
Boise City has 391,790 jobs in total (BLS, May 2025), ranking 67th by size among the 300 metros on this site.
| Trade | Weight | 25th pct | Median | 75th pct | US median | Ratio | Level used |
|---|---|---|---|---|---|---|---|
| Brickmasons and blockmasons (47-2021) | 50% | $28.30 | $30.06 | $37.48 | $29.87 | 1.01 | metro |
| Construction laborers (47-2061) | 30% | $19.98 | $22.84 | $25.18 | $22.66 | 1.01 | metro |
| Operating engineers and other construction equipment operators (47-2073) | 20% | $25.58 | $29.29 | $31.56 | $28.78 | 1.02 | metro |
| Blended | 100% | 1.01 | |||||
Retaining wall: what moves the price in Boise
Permit
Permits cost $50-$450 depending on location and wall size.
Height
Walls over 4 feet need engineering, deeper excavation and more skilled labor; many cities require permits over 3-4 feet (HomeGuide).
Material
Block, poured concrete and natural stone are priced differently; concrete and stone walls run higher than the segmental block default.
What nearby projects cost in Boise
Jobs that often go together with retaining wall are priced below at their usual sizes, using the same Boise wage and price inputs. Compared with national midpoints, sod installation comes out highest (+2%) and sprinkler system lowest (−4%); the gap comes from the trades each job uses.
| Project | Size | Range | vs. US |
|---|---|---|---|
| French drain | 60 linear ft | $610 – $2,100 | +1% |
| Paver patio | 300 sq ft | $3,000 – $5,450 | level |
| Concrete driveway | 600 sq ft | $3,550 – $8,950 | −3% |
| Sod installation | 1,500 sq ft | $1,550 – $3,350 | +2% |
| Sprinkler system | 4,000 sq ft of lawn | $3,850 – $9,650 | −4% |
| Inground pool | 450 sq ft | $35,400 – $110,500 | −2% |
Cost by quality level and size in Boise
The cited range is split into basic, standard and premium bands, then scaled to Boise. Bands overlap, because plenty of standard jobs cost as much as a light premium one. Sizes run from short garden wall (4x25 ft), 100 sq ft of wall face to 40 ft x 6 ft (240 sq ft of wall face).
Basic
$7,000 to $9,450
Short block wall, easy access
Standard
$8,850 to $11,300
Standard segmental block wall with drainage
Premium
$10,700 to $13,200
Tall or stone wall, engineered, hard access
| Size | Basic | Standard | Premium |
|---|---|---|---|
| short garden wall (4x25 ft), 100 sq ft of wall face | $3,500 – $4,850 | $4,500 – $5,850 | $5,500 – $6,800 |
| 20 ft x 4 ft (80 sq ft of wall face) | $2,800 – $3,900 | $3,650 – $4,750 | $4,450 – $5,550 |
| 40 ft x 4 ft (160 sq ft of wall face) | $5,600 – $7,600 | $7,100 – $9,150 | $8,600 – $10,600 |
| 40 ft x 6 ft (240 sq ft of wall face) | $8,350 – $11,300 | $10,600 – $13,500 | $12,800 – $15,700 |
Get 3 local quotes
Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $8,850 to $11,300 for Boise, ID is attached.
Take this estimate with you: PDF report, $9
The report lays out the retaining wall numbers for Boise, ID line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.
Retaining wall in Boise: your questions
+How much does it cost to build a retaining wall in Boise?
For 200 sq ft of wall face, expect $7,000 to $13,200 in the Boise area. A standard-spec job lands at $8,850 to $11,300. Small jobs usually cost more per sq ft of wall face and large ones less.
+What is the price per sq ft of wall face for retaining wall in Boise?
About $34.50 to $63.50 per sq ft of wall face for materials and labor, plus $50 to $440 for the permit if one is needed. The US range is $35 to $65.
+Is retaining wall cheaper in Boise or Idaho Falls?
Idaho Falls is 190 miles away. The midpoint for 200 sq ft of wall face there is $10,300, which is 2% more than Boise ($10,100). Wage and materials indexes both feed that gap.
+How much of the bill is labor in Boise?
About 47% at the midpoint, or $4,750 out of $10,100. Materials are 51% and permits 2%. Nationally, labor is 46%.
+What would 40 ft x 4 ft (160 sq ft of wall face) cost in Boise?
$5,600 to $10,600. Pick a different size in the estimator above to get your own number.
+Does retaining wall need a permit in Boise?
Often, but rules are set by your city or county building office, so call before you hire. Budget $50 to $440 for fees in the Boise area (our national range of $50 to $450 scaled by the local price level).
+Is Boise expensive for retaining wall compared with the rest of Idaho?
Boise is 0% above the Idaho statewide estimate ($10,100 at the midpoint). We cover 3 metros in Idaho; see the state page to compare them.
+What do brickmasons and blockmasons earn in Boise?
The BLS median is $30.06 an hour in the Boise area, compared with $29.87 nationally. The 25th to 75th percentile range is $28.30 to $37.48.
+What do basic and premium retaining wall work cost in Boise?
For 200 sq ft of wall face, basic work runs $7,000 to $9,450 and premium work $10,700 to $13,200. Basic means: short block wall, easy access. Premium means: tall or stone wall, engineered, hard access.
+When is the best time to build a retaining wall in Boise?
Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are March through June and September through October. June and September are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.
Retaining wall near Boise
Where these numbers come from
Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.
- HomeGuide: How Much Does a Retaining Wall Cost? (2026) (accessed November 4, 2026)
- BLS Occupational Employment and Wage Statistics, May 2025
- BEA Regional Price Parities, 2024
- NOAA NCEI U.S. Climate Normals, 1991-2020
Note on derived figures: Materials = 40% of the low installed price and 60% of the high one, since HomeGuide says labor is 40-60% of the total project cost.