Concrete slab cost in Ocala, FL

Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (400 sq ft)
$2,150 – $4,700
Per sq ft
$5.30 – $11
before permit
Versus US midpoint
−10%
US $3,850
Rank of 300 metros
#253
1 = most expensive

If you want to pour a concrete slab in Ocala, plan on $2,150 to $4,700 for 400 sq ft, all in. Per sq ft, that is $5.30 to $11 for materials and labor, with the permit on top. The local midpoint runs 10% lower than the national one. Cement masons and concrete finishers earn a median of $22.60 an hour in the Ocala area, 18% below the US median of $27.41.

Estimate your concrete slab cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

4-5 inch slab with rebar or heavier mesh and standard base prep

Add-ons

Estimated cost for 400 sq ft in Ocala, FL, standard level

$2,950 to $3,950

About $6.95 to $9.15 per sq ft before permits. Labor is about 38% of the bill.

Cost breakdown
PartLowHigh
Materials$1,600$2,250
Labor$1,150$1,400
Permits and fees$150$280
Total$2,950$3,950
Save and get a PDF report

Cost breakdown for 400 sq ft in Ocala, FL

Part of the jobLowMidpointHighShare
Materials$1,150$1,900$2,70056%
Labor$970$1,300$1,60038%
Permits and fees$50$210$3806%
Total$2,150$3,450$4,700100%

Why Ocala prices look the way they do

We price the labor side from BLS wage data for 4 trades: cement masons and concrete finishers at 50%, construction laborers at 30%, operating engineers and other construction equipment operators at 10%, carpenters at 10%. Weighted together, Ocala wages are 0.81 times the national level. Labor makes up about 38% of the midpoint estimate (42% at national prices).

On the materials line, the BEA goods price index for the Ocala metro is 96.2 (US = 100). The midpoint materials bill for 400 sq ft comes to $1,900, compared with $2,000 at national prices. Permit and inspection fees are scaled by the broader index (95.2) and land at $50 to $380.

Climate in Ocala: timing your concrete slab job

We use NOAA's 1991-2020 climate normals for Ocala (5 miles from the city center). These are 30-year monthly averages, not forecasts.

October through May is the stretch where pouring concrete runs into the fewest weather problems in Ocala (8 of 12 months). June, July, August and September have an average daytime high of 90°F or more.

Heat matters for concrete as well. With average highs of 90°F or more in June, July, August and September, crews often start early, wet the base and plan for faster set times.

Ocala gets about 52 inches of precipitation in a normal year. The wettest months are June, July and August (7.4 inches in June). Inside the workable window, April and November are the driest, at 2.2 and 2.1 inches. The station averages about 110 days a year at 90°F or above.

Does the season change the price? Probably, but we do not have a sourced seasonal price curve, so the estimator shows a year-round figure and does not adjust by month. When you collect quotes, ask whether scheduling in a slower month gets a better rate.

Monthly normals, Ocala (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan71463.4Workable
Feb74482.9Workable
Mar79523.7Workable
Apr84572.2Workable
May89643.5Workable
Jun91707.4Hot
Jul92726.9Hot
Aug92737.1Hot
Sep90706.5Hot
Oct84633.2Workable
Nov77542.1Workable
Dec72482.7Workable

Is Ocala cheap or dear? The local comparison

Contractors rarely work more than an hour or two from home, so the neighboring metros set a rough ceiling and floor for your quotes. Midpoints for 400 sq ft range from $3,450 to $3,550 across Ocala and its five closest metros.

Comparison with nearby areas
AreaRangeMidpointvs. here
Ocala, FLthis page$2,150 – $4,700$3,450
Gainesville, FL40 miles$2,200 – $4,750$3,500+1%
Deltona, FL50 miles$2,250 – $4,800$3,500+2%
Orlando, FL65 miles$2,200 – $4,800$3,500+2%
Jacksonville, FL75 miles$2,250 – $4,850$3,550+3%
Tampa, FL80 miles$2,250 – $4,850$3,550+3%
Florida (statewide)$2,250 – $4,900$3,600+5%
United States$2,450 – $5,200$3,850+11%

Across 300 US metros, Ocala comes in at #253 from the top. The priciest is Kahului, HI at $5,300; the cheapest is McAllen, TX at $3,200 (midpoints, 400 sq ft). Statewide, Ocala is 4% below the Florida figure.

Other Florida metros

Florida metros compared with Ocala
MetroSizeRangeMidpointvs. here
Miami, FL2,819,940 jobs$2,350 – $5,150$3,750+9%
Tampa, FL1,447,120 jobs$2,250 – $4,850$3,550+3%
Orlando, FL1,411,730 jobs$2,200 – $4,800$3,500+2%
Jacksonville, FL765,930 jobs$2,250 – $4,850$3,550+3%
North Port, FL339,940 jobs$2,300 – $4,900$3,600+4%
Cape Coral, FL304,790 jobs$2,250 – $4,850$3,550+3%

Cities with a workforce like Ocala's

Big cities and small ones price differently, so here is Ocala against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
Kalamazoo, MI121,790 jobs$2,350 – $5,000$3,700+7%
Erie, PA120,480 jobs$2,450 – $5,200$3,800+11%
San Luis Obispo, CA122,020 jobs$2,750 – $5,750$4,250+23%
Burlington, VT120,150 jobs$2,500 – $5,250$3,900+13%

Planning more than one job in Ocala?

Because every project leans on different trades, Ocala's wage level does not move all prices equally. Against the US midpoint, asphalt driveway runs −9% and concrete driveway −14%.

Related projects with local prices
ProjectSizeRangevs. US
Concrete driveway600 sq ft$3,150 – $7,850−14%
Concrete patio300 sq ft$1,150 – $3,500−12%
Detached garage576 sq ft$25,400 – $50,900−12%
Stamped concrete400 sq ft$2,900 – $7,050−11%
Asphalt driveway600 sq ft$2,800 – $6,700−9%
Gravel driveway1,000 sq ft$2,200 – $8,950−12%

Specs and site conditions that change a Ocala bid

  • Thickness and mix

    A 4-inch slab uses about 1.23 cubic yards of concrete per 100 sq ft; a 6-inch slab uses about 1.85. Stepping up from a 3,000 PSI to a 4,000-4,500 PSI mix adds $10-$40 per cubic yard (Estimators.us).

  • Base and reinforcement

    A compacted gravel base, vapor barrier, and wire mesh or rebar are priced separately by some contractors and bundled by others. Ask which one your quote does.

  • Truck and pump access

    If the mixer truck can't back up to the forms, someone has to wheelbarrow it in or hire a pump. Pump or line-pump hire is typically billed per day.

Ocala: what basic, standard and premium work costs

Three bands are cut from the same cited range and localized for Ocala wages and prices. They overlap on purpose: a good standard job and a modest premium job can cost the same. The grid below prices the same bands at 5 common sizes.

Basic

$2,150 to $3,200

4-inch broom-finish slab, light mesh, easy truck access

Standard

$2,950 to $3,950

4-5 inch slab with rebar or heavier mesh and standard base prep

Premium

$3,700 to $4,700

6-inch slab, heavy reinforcement, thick base, pump truck or tight access

Cost by size and quality level
SizeBasicStandardPremium
10x10 pad (100 sq ft)$580 – $930$840 – $1,200$1,100 – $1,450
12x12 (144 sq ft)$810 – $1,250$1,150 – $1,600$1,500 – $1,950
20x20 (400 sq ft)$2,150 – $3,200$2,950 – $3,950$3,700 – $4,700
24x24 garage floor (576 sq ft)$3,100 – $4,500$4,150 – $5,550$5,200 – $6,600
30x40 foundation (1,200 sq ft)$6,400 – $9,200$8,500 – $11,300$10,600 – $13,300

Extras that change the Ocala total

Extras are quoted nationally and then scaled to Ocala by the average of the local wage index (0.81) and goods index (0.96), a factor of 0.89. Tick any of them in the estimator above to add them to your total. Treat these as planning figures: an add-on touches different trades than the main job, so the scaling is an approximation.

Add-on prices
Add-onLocal range
Add rebar reinforcement$350 – $1,050
Remove old concrete first$710 – $2,150

Ocala labor market for concrete slab

Wages are the part of this estimate that changes most from town to town. 4 trades carry the job here, and each is compared with its US median. The weighted result for Ocala is 0.81 times the national level.

For cement masons and concrete finishers (47-2051, weighted 50%) the local median is $22.60 an hour, which is 18% below the national $27.41. The middle half of them earn between $18.48 and $24.74 an hour. BLS counts 250 of them working in the area, 20.7 for every 10,000 jobs (US: 13.3), so the local bench is deeper than average.

Construction laborers (47-2061), 30% of the weighting: a median of $18.29 an hour, 19% below the US median of $22.66. The middle half of them earn between $16.84 and $21.63 an hour. About 1,340 work in the metro. That is 110.8 per 10,000 jobs, compared with 70.5 nationally, which suggests plenty of local crews to bid.

For operating engineers and other construction equipment operators (47-2073, weighted 10%) the local median is $22.35 an hour, which is 22% below the national $28.78. The middle half of them earn between $18.50 and $24.33 an hour. BLS counts 460 of them working in the area, 38.0 for every 10,000 jobs (US: 30.7), so the local bench is deeper than average.

For carpenters (47-2031, weighted 10%) the local median is $22.41 an hour, which is 23% below the national $29.12. The middle half of them earn between $19.00 and $26.57 an hour. BLS counts 490 of them working in the area, 40.5 for every 10,000 jobs (US: 43.1), so the local bench is about average.

Quotes come from real crews, not medians. If the cement masons and concrete finishers on your job are paid at the 75th percentile ($24.74 an hour) instead of the median, the labor line grows by about $60. At the 25th percentile ($18.48) it shrinks by about $120. The total moves by 1.8% or 3.5%, so wages alone rarely explain a quote that is far outside our range.

For context on the local economy, BLS counts 120,980 jobs in the Ocala area. That makes it the 180th largest of the 300 metros we cover, with 0.08% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)50%$18.48$22.60$24.74$27.410.82metro
Construction laborers (47-2061)30%$16.84$18.29$21.63$22.660.81metro
Operating engineers and other construction equipment operators (47-2073)10%$18.50$22.35$24.33$28.780.78metro
Carpenters (47-2031)10%$19.00$22.41$26.57$29.120.77metro
Blended100%0.81

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $2,950 to $3,950 for Ocala, FL is attached.

Take this estimate with you: PDF report, $9

The report lays out the concrete slab numbers for Ocala, FL line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Concrete slab in Ocala: your questions

+How much does it cost to pour a concrete slab in Ocala?

For 400 sq ft, expect $2,150 to $4,700 in the Ocala area. A standard-spec job lands at $2,950 to $3,950. Small jobs usually cost more per sq ft and large ones less.

+What is the price per sq ft for concrete slab in Ocala?

About $5.30 to $11 per sq ft for materials and labor, plus $50 to $380 for the permit if one is needed. The US range is $6 to $12.

+Is concrete slab cheaper in Ocala or Gainesville?

Gainesville is 40 miles away. The midpoint for 400 sq ft there is $3,500, which is 1% more than Ocala ($3,450). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Ocala?

About 38% at the midpoint, or $1,300 out of $3,450. Materials are 56% and permits 6%. Nationally, labor is 42%.

+What would 20x20 (400 sq ft) cost in Ocala?

$2,150 to $4,700. Pick a different size in the estimator above to get your own number.

+Does concrete slab need a permit in Ocala?

Often, but rules are set by your city or county building office, so call before you hire. Budget $50 to $380 for fees in the Ocala area (our national range of $50 to $400 scaled by the local price level).

+Is Ocala expensive for concrete slab compared with the rest of Florida?

Ocala is 4% below the Florida statewide estimate ($3,600 at the midpoint). We cover 19 metros in Florida; see the state page to compare them.

+What do cement masons and concrete finishers earn in Ocala?

The BLS median is $22.60 an hour in the Ocala area, compared with $27.41 nationally. The 25th to 75th percentile range is $18.48 to $24.74.

+What do basic and premium concrete slab work cost in Ocala?

For 400 sq ft, basic work runs $2,150 to $3,200 and premium work $3,700 to $4,700. Basic means: 4-inch broom-finish slab, light mesh, easy truck access. Premium means: 6-inch slab, heavy reinforcement, thick base, pump truck or tight access.

+When is the best time to pour a concrete slab in Ocala?

Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are October through May. April and November are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.

+What does "add rebar reinforcement" add in Ocala?

$350 to $1,050 for 400 sq ft, from a national range scaled by the local wage and goods indexes.

Concrete slab near Ocala

Concrete slab: all pricesConcrete slab in FloridaAll projects in OcalaFlorida cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.