Stamped concrete cost in Seattle, WA
Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.
- Typical range (400 sq ft)
- $3,850 – $9,700
- Per sq ft
- $9.55 – $23.50
- before permit
- Versus US midpoint
- +21%
- US $5,600
- Rank of 300 metros
- #7
- 1 = most expensive
Seattle homeowners pay roughly $3,850 to $9,700 to pour stamped concrete at 400 sq ft, or $9.55 to $23.50 per sq ft (permit not included). Against the US midpoint, Seattle is 21% higher. Cement masons and concrete finishers earn a median of $38.88 an hour in the Seattle area, 42% above the US median of $27.41.
Estimate your stamped concrete cost
Pick a size, a quality level and where you live. Prices update as you type.
Estimated cost for 400 sq ft in Seattle, WA, standard level
$5,600 to $7,950
About $13.50 to $19 per sq ft before permits. Labor is about 55% of the bill.
| Part | Low | High |
|---|---|---|
| Materials | $2,450 | $3,200 |
| Labor | $3,050 | $4,500 |
| Permits and fees | $160 | $290 |
| Total | $5,600 | $7,950 |
Cost breakdown for 400 sq ft in Seattle, WA
| Part of the job | Low | Midpoint | High | Share |
|---|---|---|---|---|
| Materials | $1,850 | $2,800 | $3,750 | 41% |
| Labor | $1,950 | $3,750 | $5,550 | 55% |
| Permits and fees | $55 | $220 | $390 | 3% |
| Total | $3,850 | $6,800 | $9,700 | 100% |
What is behind the Seattle number
We price the labor side from BLS wage data for 3 trades: cement masons and concrete finishers at 60%, construction laborers at 30%, operating engineers and other construction equipment operators at 10%. Weighted together, Seattle wages are 1.39 times the national level. Labor makes up about 55% of the midpoint estimate (48% at national prices).
On the materials line, the BEA goods price index for the Seattle metro is 104.0 (US = 100). The midpoint materials bill for 400 sq ft comes to $2,800, compared with $2,700 at national prices. Permit and inspection fees are scaled by the broader index (111.1) and land at $55 to $390.
How Seattle compares
Contractors rarely work more than an hour or two from home, so the neighboring metros set a rough ceiling and floor for your quotes. Midpoints for 400 sq ft range from $6,450 to $6,800 across Seattle and its five closest metros.
| Area | Range | Midpoint | vs. here |
|---|---|---|---|
| Seattle, WAthis page | $3,850 – $9,700 | $6,800 | |
| Bremerton, WA40 miles | $3,750 – $9,350 | $6,550 | −4% |
| Olympia, WA60 miles | $3,750 – $9,400 | $6,600 | −3% |
| Yakima, WA90 miles | $3,850 – $9,550 | $6,700 | −1% |
| Bellingham, WA95 miles | $3,800 – $9,500 | $6,650 | −2% |
| Portland, OR135 miles | $3,700 – $9,250 | $6,450 | −5% |
| Washington (statewide) | $3,800 – $9,400 | $6,600 | −3% |
| United States | $3,250 – $7,950 | $5,600 | −17% |
Across 300 US metros, Seattle comes in at #7 from the top. The priciest is Kahului, HI at $8,150; the cheapest is McAllen, TX at $4,550 (midpoints, 400 sq ft). Statewide, Seattle is 3% above the Washington figure.
Other Washington metros
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Spokane, WA | 255,820 jobs | $3,700 – $9,100 | $6,400 | −6% |
| Olympia, WA | 130,300 jobs | $3,750 – $9,400 | $6,600 | −3% |
| Kennewick, WA | 129,490 jobs | $3,750 – $9,300 | $6,550 | −4% |
| Yakima, WA | 97,010 jobs | $3,850 – $9,550 | $6,700 | −1% |
| Bremerton, WA | 93,740 jobs | $3,750 – $9,350 | $6,550 | −4% |
| Bellingham, WA | 91,390 jobs | $3,800 – $9,500 | $6,650 | −2% |
Cities with a workforce like Seattle's
Big cities and small ones price differently, so here is Seattle against the 4 metros with the closest total employment.
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| San Francisco, CA | 2,373,920 jobs | $4,050 – $10,200 | $7,150 | +5% |
| Minneapolis, MN | 1,951,650 jobs | $3,750 – $9,250 | $6,500 | −4% |
| Phoenix, AZ | 2,375,760 jobs | $3,200 – $7,900 | $5,550 | −18% |
| Detroit, MI | 1,904,530 jobs | $3,400 – $8,450 | $5,950 | −13% |
Planning more than one job in Seattle?
Because every project leans on different trades, Seattle's wage level does not move all prices equally. Against the US midpoint, concrete driveway runs +27% and concrete slab +18%.
| Project | Size | Range | vs. US |
|---|---|---|---|
| Concrete patio | 300 sq ft | $1,450 – $4,950 | +22% |
| Concrete driveway | 600 sq ft | $4,550 – $11,800 | +27% |
| Paver patio | 300 sq ft | $3,700 – $6,750 | +23% |
| Concrete slab | 400 sq ft | $2,950 – $6,100 | +18% |
| Asphalt driveway | 600 sq ft | $3,750 – $9,450 | +26% |
| Gravel driveway | 1,000 sq ft | $3,100 – $12,600 | +24% |
Specs and site conditions that change a Seattle bid
Sealing and vapor barrier
Sealer is usually quoted separately; vapor barrier material is $0.20-$1.50 per sq ft depending on thickness (HomeGuide).
Not included
These prices don't include site prep that depends on the project: demolition, grading, or a thicker base.
Pattern and color
Basic to average coloring runs $8-$19 per sq ft. A 2-car stamped driveway runs $12-$18 per sq ft (HomeGuide); Estimators.us puts decorative slabs at $15-$30.
Pick a size, pick a tier: stamped concrete pricing in Seattle
Three bands are cut from the same cited range and localized for Seattle wages and prices. They overlap on purpose: a good standard job and a modest premium job can cost the same. The grid below prices the same bands at 3 common sizes.
Basic
$3,850 to $6,200
Basic pattern, one integral color
Standard
$5,600 to $7,950
Two-tone color release and a border
Premium
$7,350 to $9,700
Multi-color, hand-detailed, sealed to a high finish
| Size | Basic | Standard | Premium |
|---|---|---|---|
| 10x20 patio (200 sq ft) | $1,950 – $3,200 | $2,900 – $4,100 | $3,800 – $5,050 |
| 20x20 patio (400 sq ft) | $3,850 – $6,200 | $5,600 – $7,950 | $7,350 – $9,700 |
| 2-car driveway (600 sq ft) | $5,800 – $9,200 | $8,350 – $11,800 | $10,900 – $14,400 |
Optional extras in Seattle
Extras are quoted nationally and then scaled to Seattle by the average of the local wage index (1.39) and goods index (1.04), a factor of 1.22. Tick any of them in the estimator above to add them to your total. Treat these as planning figures: an add-on touches different trades than the main job, so the scaling is an approximation.
| Add-on | Local range |
|---|---|
| Add a vapor barrier | $240 – $490 |
When to schedule stamped concrete in Seattle
We use NOAA's 1991-2020 climate normals for Seattle Sand Pt Wsfo (5 miles from the city center). These are 30-year monthly averages, not forecasts.
April through November is the stretch where pouring concrete runs into the fewest weather problems in Seattle (8 of 12 months). January, February, March and December have an average overnight low of 40°F or below.
The 40°F line is a deliberately cautious stand-in. The American Concrete Institute's cold-weather guide (ACI 306R-16) defines cold-weather concreting around an average daily air temperature below 40°F, which is colder than our test of an average overnight low at or below 40°F, so we flag a few extra shoulder months. In cold weather crews may need heated enclosures, insulating blankets or accelerated mixes, and those measures can raise a quote.
Seattle gets about 38 inches of precipitation in a normal year, including roughly 4 inches of snow. The wettest months are January, November and December (5.8 inches in November). Inside the workable window, July and August are the driest, at 0.8 and 1.0 inches. The station averages about 2 days a year at 90°F or above.
Does the season change the price? Probably, but we do not have a sourced seasonal price curve, so the estimator shows a year-round figure and does not adjust by month. When you collect quotes, ask whether scheduling in a slower month gets a better rate.
| Month | Avg high °F | Avg low °F | Precip (in) | For this job |
|---|---|---|---|---|
| Jan | 47 | 37 | 5.1 | Cold |
| Feb | 50 | 37 | 3.5 | Cold |
| Mar | 54 | 39 | 3.9 | Cold |
| Apr | 59 | 43 | 3.0 | Workable |
| May | 65 | 48 | 2.2 | Workable |
| Jun | 70 | 53 | 1.6 | Workable |
| Jul | 77 | 57 | 0.8 | Workable |
| Aug | 77 | 57 | 1.0 | Workable |
| Sep | 71 | 53 | 1.7 | Workable |
| Oct | 61 | 47 | 3.6 | Workable |
| Nov | 52 | 41 | 5.8 | Workable |
| Dec | 47 | 37 | 5.5 | Cold |
Local wages behind the labor line
Wages are the part of this estimate that changes most from town to town. 3 trades carry the job here, and each is compared with its US median. The weighted result for Seattle is 1.39 times the national level.
For cement masons and concrete finishers (47-2051, weighted 60%) the local median is $38.88 an hour, which is 42% above the national $27.41. The middle half of them earn between $29.14 and $52.52 an hour. BLS counts 2,140 of them working in the area, 10.3 for every 10,000 jobs (US: 13.3), so the local bench is thinner than average.
Construction laborers (47-2061), 30% of the weighting: a median of $28.72 an hour, 27% above the US median of $22.66. The middle half of them earn between $23.67 and $37.03 an hour. About 13,040 work in the metro. That is 62.5 per 10,000 jobs, compared with 70.5 nationally, so the supply of crews looks typical.
For operating engineers and other construction equipment operators (47-2073, weighted 10%) the local median is $46.04 an hour, which is 60% above the national $28.78. The middle half of them earn between $36.13 and $58.78 an hour. BLS counts 4,860 of them working in the area, 23.3 for every 10,000 jobs (US: 30.7), so the local bench is thinner than average.
Quotes come from real crews, not medians. If the cement masons and concrete finishers on your job are paid at the 75th percentile ($52.52 an hour) instead of the median, the labor line grows by about $810. At the 25th percentile ($29.14) it shrinks by about $580. The total moves by 11.9% or 8.5%, so wages alone rarely explain a quote that is far outside our range.
For context on the local economy, BLS counts 2,086,210 jobs in the Seattle-Tacoma-Bellevue area. That makes it the 13th largest of the 300 metros we cover, with 1.34% of US employment.
| Trade | Weight | 25th pct | Median | 75th pct | US median | Ratio | Level used |
|---|---|---|---|---|---|---|---|
| Cement masons and concrete finishers (47-2051) | 60% | $29.14 | $38.88 | $52.52 | $27.41 | 1.42 | metro |
| Construction laborers (47-2061) | 30% | $23.67 | $28.72 | $37.03 | $22.66 | 1.27 | metro |
| Operating engineers and other construction equipment operators (47-2073) | 10% | $36.13 | $46.04 | $58.78 | $28.78 | 1.60 | metro |
| Blended | 100% | 1.39 | |||||
Get 3 local quotes
Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $5,600 to $7,950 for Seattle, WA is attached.
Take this estimate with you: PDF report, $9
The report lays out the stamped concrete numbers for Seattle, WA line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.
Stamped concrete in Seattle: your questions
+How much does it cost to pour stamped concrete in Seattle?
For 400 sq ft, expect $3,850 to $9,700 in the Seattle area. A standard-spec job lands at $5,600 to $7,950. Small jobs usually cost more per sq ft and large ones less.
+What is the price per sq ft for stamped concrete in Seattle?
About $9.55 to $23.50 per sq ft for materials and labor, plus $55 to $390 for the permit if one is needed. The US range is $8 to $19.
+Is stamped concrete cheaper in Seattle or Bremerton?
Bremerton is 40 miles away. The midpoint for 400 sq ft there is $6,550, which is 4% less than Seattle ($6,800). Wage and materials indexes both feed that gap.
+How much of the bill is labor in Seattle?
About 55% at the midpoint, or $3,750 out of $6,800. Materials are 41% and permits 3%. Nationally, labor is 48%.
+What would 20x20 patio (400 sq ft) cost in Seattle?
$3,850 to $9,700. Pick a different size in the estimator above to get your own number.
+Does stamped concrete need a permit in Seattle?
Often, but rules are set by your city or county building office, so call before you hire. Budget $55 to $390 for fees in the Seattle area (our national range of $50 to $350 scaled by the local price level).
+Is Seattle expensive for stamped concrete compared with the rest of Washington?
Seattle is 3% above the Washington statewide estimate ($6,600 at the midpoint). We cover 7 metros in Washington; see the state page to compare them.
+What do cement masons and concrete finishers earn in Seattle?
The BLS median is $38.88 an hour in the Seattle area, compared with $27.41 nationally. The 25th to 75th percentile range is $29.14 to $52.52.
+What do basic and premium stamped concrete work cost in Seattle?
For 400 sq ft, basic work runs $3,850 to $6,200 and premium work $7,350 to $9,700. Basic means: basic pattern, one integral color. Premium means: multi-color, hand-detailed, sealed to a high finish.
+When is the best time to pour stamped concrete in Seattle?
Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are April through November. July and August are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.
+What does "add a vapor barrier" add in Seattle?
$240 to $490 for 400 sq ft, from a national range scaled by the local wage and goods indexes.
Stamped concrete near Seattle
Where these numbers come from
Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.
- HomeGuide: How Much Does Stamped Concrete Cost? (2026) (accessed November 4, 2026)
- SimplyWise: Concrete Estimate Template: Free PDF + Excel (2026) (accessed November 4, 2026)
- BLS Occupational Employment and Wage Statistics, May 2025
- BEA Regional Price Parities, 2024
- NOAA NCEI U.S. Climate Normals, 1991-2020
Note on derived figures: Materials = SimplyWise's 200 sq ft stamped-patio line ($900-$1,800), divided by 200 sq ft.