Skip to content
CostLocal

Concrete slab cost in Nevada

Statewide estimate from BLS wages and BEA prices. Reviewed Nov 4, 2026.

Statewide range (400 sq ft)
$2,500 – $5,250
Per sq ft
$6.10 – $12
before permit
Versus US midpoint
+1%
US $3,850
Metros covered
2

What does it cost to pour a concrete slab in Nevada? Plan on $2,500 to $5,250 for 400 sq ft. Wages (1.07x the US blend), materials (price index 96.3) and permit costs (100.0) put the state above the national midpoint by 1%.

Inside Nevada, the metros we cover range from $3,850 (Las Vegas) to $3,900 (Reno) at the midpoint.

Estimate your concrete slab cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

4-5 inch slab with rebar or heavier mesh and standard base prep

Add-ons

Estimated cost for 400 sq ft in Nevada (statewide), standard level

$3,300 to $4,400

About $7.90 to $10.50 per sq ft before permits. Labor is about 44% of the bill.

Cost breakdown
PartLowHigh
Materials$1,600$2,250
Labor$1,550$1,900
Permits and fees$150$290
Total$3,300$4,400
Save and get a PDF report

Cost breakdown for 400 sq ft in Nevada

Part of the jobLowMidpointHighShare
Materials$1,150$1,950$2,70050%
Labor$1,300$1,700$2,15044%
Permits and fees$50$220$4006%
Total$2,500$3,850$5,250100%

Nevada against its neighbors

Nevada ranks 20 of 51 (the 50 states plus DC) for concrete slab, where 1 is the most expensive. The costliest is Hawaii at $5,150 and the cheapest Arkansas at $3,350, both for 400 sq ft at the midpoint. Nevada sits at $3,850. The five states closest by workforce center are listed below.

States near Nevada, same project and size
StateDistanceRangeMidpointvs. here
California210 miles away$2,750 – $5,800$4,300+11%
Utah290 miles away$2,400 – $5,050$3,700−4%
Arizona340 miles away$2,400 – $5,100$3,750−3%
Idaho460 miles away$2,400 – $5,050$3,700−4%
New Mexico550 miles away$2,250 – $4,800$3,500−9%

What cement masons and concrete finishers and the other trades earn in Nevada

Statewide wages come from BLS's state-level estimates, which blend big cities with small towns and rural areas. 4 trades drive the labor line for this job, and the weighted ratio against the national wage level is 1.07 for Nevada.

For cement masons and concrete finishers (47-2051, weighted 50%) the local median is $29.44 an hour, which is 7% above the national $27.41. The middle half of them earn between $24.17 and $36.42 an hour. BLS counts 3,290 of them working in the state, 21.2 for every 10,000 jobs (US: 13.3), so the local bench is deeper than average.

Construction laborers (47-2061), 30% of the weighting: a median of $23.55 an hour, 4% above the US median of $22.66. The middle half of them earn between $20.22 and $31.12 an hour. About 11,890 work in the state. That is 76.6 per 10,000 jobs, compared with 70.5 nationally, so the supply of crews looks typical.

For operating engineers and other construction equipment operators (47-2073, weighted 10%) the local median is $34.33 an hour, which is 19% above the national $28.78. The middle half of them earn between $29.19 and $43.29 an hour. BLS counts 5,410 of them working in the state, 34.9 for every 10,000 jobs (US: 30.7), so the local bench is about average.

For carpenters (47-2031, weighted 10%) the local median is $29.99 an hour, which is in line with the national $29.12. The middle half of them earn between $24.25 and $39.13 an hour. BLS counts 12,700 of them working in the state, 81.9 for every 10,000 jobs (US: 43.1), so the local bench is deeper than average.

A crew paid at the 75th percentile for cement masons and concrete finishers ($36.42 an hour) would add about $200 to the statewide midpoint; one at the 25th percentile ($24.17) would take off about $150. Use that as a rough guide to how far a bid can sit from our midpoint on wages alone.

BLS counts 1,551,540 jobs across Nevada (May 2025), which is 1.0% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)50%$24.17$29.44$36.42$27.411.07state
Construction laborers (47-2061)30%$20.22$23.55$31.12$22.661.04state
Operating engineers and other construction equipment operators (47-2073)10%$29.19$34.33$43.29$28.781.19state
Carpenters (47-2031)10%$24.25$29.99$39.13$29.121.03state
Blended100%1.07

Nevada metro-by-metro prices

1 of the 2 metros sit above the statewide midpoint of $3,850, and the top-to-bottom gap is 2%. Each row prices the default size with that metro's own BLS wages and BEA price levels, so the gap between rows is real local variation rather than a flat markup.

MetroRange (400 sq ft)Midpointvs. state
Reno, NV$2,500 – $5,300$3,900+1%
Las Vegas, NV$2,450 – $5,200$3,850−1%

Concrete slab: what moves the price in Nevada

  • Thickness and mix

    A 4-inch slab uses about 1.23 cubic yards of concrete per 100 sq ft; a 6-inch slab uses about 1.85. Stepping up from a 3,000 PSI to a 4,000-4,500 PSI mix adds $10-$40 per cubic yard (Estimators.us).

  • Base and reinforcement

    A compacted gravel base, vapor barrier, and wire mesh or rebar are priced separately by some contractors and bundled by others. Ask which one your quote does.

  • Truck and pump access

    If the mixer truck can't back up to the forms, someone has to wheelbarrow it in or hire a pump. Pump or line-pump hire is typically billed per day.

  • Small-job minimums

    Many crews have a minimum charge, so a 10x10 pad can cost more per square foot than a 20x20 slab.

  • Finish

    A broom finish is the baseline. Stamped, stained, or exposed-aggregate finishes are priced as add-ons on top of the slab.

Optional extras in Nevada

Extras are quoted nationally and then scaled to Nevada by the average of the local wage index (1.07) and goods index (0.96), a factor of 1.02. Tick any of them in the estimator above to add them to your total. Treat these as planning figures: an add-on touches different trades than the main job, so the scaling is an approximation.

Add-on prices
Add-onLocal range
Add rebar reinforcement$410 – $1,200
Remove old concrete first$810 – $2,450

Other Nevada jobs that often go with concrete slab

The table prices neighboring jobs at their usual sizes using statewide Nevada wages and prices. Against national midpoints, gravel driveway comes out highest (+4%) and asphalt driveway lowest (level), because each job leans on different trades.

Related projects with local prices
ProjectSizeRangevs. US
Concrete driveway600 sq ft$3,750 – $9,600+4%
Concrete patio300 sq ft$1,250 – $4,100+2%
Detached garage576 sq ft$29,000 – $58,200level
Stamped concrete400 sq ft$3,300 – $8,100+2%
Asphalt driveway600 sq ft$3,050 – $7,450level
Gravel driveway1,000 sq ft$2,600 – $10,600+4%

When Nevada weather lets you pour

Season matters for concrete slab. For each Nevada metro below we took NOAA's 1991-2020 monthly normals from the nearest suitable station and counted comfortable months for pouring concrete.

Las Vegas has the longest comfortable season of the metros we cover in Nevada at 6 months (February through May and October through November); Reno has the shortest at 3 (May through June and September). Rainfall runs from 4 inches a year in Las Vegas to 7 inches in Reno.

We do not adjust prices by month, because we have no reliable published data on seasonal pricing. Timing is still worth raising when you collect bids.

Climate by metro (NOAA 1991-2020 normals)
MetroJan avg low °FJul avg high °FPrecip (in/yr)Comfortable months
Las Vegas3910446: February through May and October through November
Reno269473: May through June and September

Quality levels and sizes in Nevada

The cited range is cut into three overlapping bands (basic, standard and premium) and scaled to statewide Nevada wages and prices. The grid prices the same bands at 5 common sizes.

Basic

$2,500 to $3,600

4-inch broom-finish slab, light mesh, easy truck access

Standard

$3,300 to $4,400

4-5 inch slab with rebar or heavier mesh and standard base prep

Premium

$4,150 to $5,250

6-inch slab, heavy reinforcement, thick base, pump truck or tight access

Cost by size and quality level
SizeBasicStandardPremium
10x10 pad (100 sq ft)$660 – $1,050$940 – $1,300$1,250 – $1,600
12x12 (144 sq ft)$930 – $1,400$1,300 – $1,800$1,650 – $2,150
20x20 (400 sq ft)$2,500 – $3,600$3,300 – $4,400$4,150 – $5,250
24x24 garage floor (576 sq ft)$3,550 – $5,100$4,700 – $6,250$5,850 – $7,350
30x40 foundation (1,200 sq ft)$7,350 – $10,400$9,650 – $12,700$11,900 – $14,900

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $3,300 to $4,400 for Nevada is attached.

Take this estimate with you: PDF report, $9

Multi-page report for Nevada: low, typical and high cost, a line-item breakdown of materials and labor by trade, permit notes, the best months to schedule, a quote comparison sheet, red flags, questions for contractors, checklists and every source. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Concrete slab in Nevada: your questions

+How much does it cost to pour a concrete slab in Nevada?

$2,500 to $5,250 for 400 sq ft, using statewide wages and prices. Metro areas inside Nevada can sit above or below that.

+Which city in Nevada is cheapest for concrete slab?

Las Vegas at about $3,850 (midpoint, 400 sq ft). The priciest is Reno at $3,900.

+Is concrete slab cheaper in Nevada than the US average?

It is 1% more expensive: $3,850 against $3,850 for 400 sq ft at the midpoint.

+What share of the price is labor in Nevada?

About 44% ($1,700). Materials are 50%. Statewide labor for this job is weighted 1.07x the national wage level.

+Does a concrete slab need a permit?

Often yes if it's structural (a garage floor or foundation) and often no for a small at-grade pad. Permit fees run $50-$400 depending on the city (HomeGuide).

+What do cement masons and concrete finishers earn in Nevada?

The BLS statewide median is $29.44 an hour, against $27.41 for the US. The 25th to 75th percentile range is $24.17 to $36.42.

+Where does Nevada rank for concrete slab costs?

20th most expensive of 51 (the 50 states plus DC) at the midpoint, $3,850 for 400 sq ft. Rank 1 is the costliest.

+What do basic and premium concrete slab work cost in Nevada?

For 400 sq ft, basic work runs $2,500 to $3,600 and premium work $4,150 to $5,250. Basic means: 4-inch broom-finish slab, light mesh, easy truck access. Premium means: 6-inch slab, heavy reinforcement, thick base, pump truck or tight access.

+Does the season matter for concrete slab in Nevada?

Yes where winters or summers are hard. Of the Nevada metros we cover, Las Vegas has the most comfortable months (6 of 12) based on NOAA 1991-2020 normals. Our prices do not change by month, so ask contractors whether they charge more or less in busy and slow seasons.

+What does "add rebar reinforcement" add in Nevada?

$410 to $1,200 for 400 sq ft, from a national range scaled by the statewide wage and goods indexes.

Concrete slab by city in Nevada

Concrete slab: all pricesNevada cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.