Statewide estimate from BLS wages and BEA prices. Reviewed Nov 4, 2026.

Statewide range (400 sq ft)
$2,400 – $5,050
Per sq ft
$5.85 – $11.50
before permit
Versus US midpoint
−3%
US $3,850
Metros covered
3

Idaho prices for concrete slab: $2,400 to $5,050 for 400 sq ft, or $5.85 to $11.50 per sq ft without the permit. The state midpoint is 3% below the national one. Local wages for cement masons and concrete finishers are $27.12 an hour.

Inside Idaho, the metros we cover range from $3,650 (Idaho Falls) to $3,800 (Coeur d'Alene) at the midpoint. Pick your closest city in the table for a tighter number.

Estimate your concrete slab cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

4-5 inch slab with rebar or heavier mesh and standard base prep

Add-ons

Estimated cost for 400 sq ft in Idaho (statewide), standard level

$3,200 to $4,250

About $7.60 to $9.90 per sq ft before permits. Labor is about 42% of the bill.

Cost breakdown
PartLowHigh
Materials$1,600$2,250
Labor$1,400$1,750
Permits and fees$150$280
Total$3,200$4,250
Save and get a PDF report

Cost breakdown for 400 sq ft in Idaho

Part of the jobLowMidpointHighShare
Materials$1,150$1,950$2,70052%
Labor$1,200$1,550$1,95042%
Permits and fees$50$210$3806%
Total$2,400$3,700$5,050100%

Idaho against its neighbors

Idaho ranks 32 of 51 (the 50 states plus DC) for concrete slab, where 1 is the most expensive. The costliest is Hawaii at $5,150 and the cheapest Arkansas at $3,350, both for 400 sq ft at the midpoint. Idaho sits at $3,700. The five states closest by workforce center are listed below.

States near Idaho, same project and size
StateDistanceRangeMidpointvs. here
Montana270 miles away$2,450 – $5,200$3,850+3%
Utah280 miles away$2,400 – $5,050$3,700level
Oregon350 miles away$2,700 – $5,650$4,200+13%
Washington380 miles away$2,850 – $5,950$4,400+19%
Nevada460 miles away$2,500 – $5,250$3,850+4%

Idaho seasons and concrete slab

Season matters for concrete slab. For each Idaho metro below we took NOAA's 1991-2020 monthly normals from the nearest suitable station and counted comfortable months for pouring concrete.

Coeur d'Alene has the longest comfortable season of the metros we cover in Idaho at 5 months (May through September); Idaho Falls has the shortest at 4 (June through September). Rainfall runs from 10 inches a year in Idaho Falls to 25 inches in Coeur d'Alene.

We do not adjust prices by month, because we have no reliable published data on seasonal pricing. Timing is still worth raising when you collect bids.

Climate by metro (NOAA 1991-2020 normals)
MetroJan avg low °FJul avg high °FPrecip (in/yr)Comfortable months
Boise2693124: May through June and September through October
Idaho Falls1287104: June through September
Coeur d'Alene2683255: May through September

Quality levels and sizes in Idaho

The cited range is cut into three overlapping bands (basic, standard and premium) and scaled to statewide Idaho wages and prices. The grid prices the same bands at 5 common sizes.

Basic

$2,400 to $3,450

4-inch broom-finish slab, light mesh, easy truck access

Standard

$3,200 to $4,250

4-5 inch slab with rebar or heavier mesh and standard base prep

Premium

$4,000 to $5,050

6-inch slab, heavy reinforcement, thick base, pump truck or tight access

Cost by size and quality level
SizeBasicStandardPremium
10x10 pad (100 sq ft)$630 – $1,000$910 – $1,250$1,200 – $1,550
12x12 (144 sq ft)$890 – $1,350$1,250 – $1,700$1,600 – $2,050
20x20 (400 sq ft)$2,400 – $3,450$3,200 – $4,250$4,000 – $5,050
24x24 garage floor (576 sq ft)$3,400 – $4,900$4,500 – $6,000$5,600 – $7,100
30x40 foundation (1,200 sq ft)$7,050 – $10,000$9,250 – $12,200$11,400 – $14,400

Related projects, priced for Idaho

The table prices neighboring jobs at their usual sizes using statewide Idaho wages and prices. Against national midpoints, asphalt driveway comes out highest (+4%) and detached garage lowest (−5%), because each job leans on different trades.

Related projects with local prices
ProjectSizeRangevs. US
Concrete driveway600 sq ft$3,550 – $9,000−2%
Concrete patio300 sq ft$1,200 – $3,900−3%
Detached garage576 sq ft$27,500 – $55,200−5%
Stamped concrete400 sq ft$3,200 – $7,800−2%
Asphalt driveway600 sq ft$3,150 – $7,750+4%
Gravel driveway1,000 sq ft$2,450 – $10,100−1%

Concrete slab: what moves the price in Idaho

  • Thickness and mix

    A 4-inch slab uses about 1.23 cubic yards of concrete per 100 sq ft; a 6-inch slab uses about 1.85. Stepping up from a 3,000 PSI to a 4,000-4,500 PSI mix adds $10-$40 per cubic yard (Estimators.us).

  • Base and reinforcement

    A compacted gravel base, vapor barrier, and wire mesh or rebar are priced separately by some contractors and bundled by others. Ask which one your quote does.

  • Truck and pump access

    If the mixer truck can't back up to the forms, someone has to wheelbarrow it in or hire a pump. Pump or line-pump hire is typically billed per day.

  • Small-job minimums

    Many crews have a minimum charge, so a 10x10 pad can cost more per square foot than a 20x20 slab.

  • Finish

    A broom finish is the baseline. Stamped, stained, or exposed-aggregate finishes are priced as add-ons on top of the slab.

Which Idaho city is cheapest for concrete slab?

1 of the 3 metros sit above the statewide midpoint of $3,700, and the top-to-bottom gap is 4%. Each row prices the default size with that metro's own BLS wages and BEA price levels, so the gap between rows is real local variation rather than a flat markup.

MetroRange (400 sq ft)Midpointvs. state
Coeur d'Alene, ID$2,450 – $5,150$3,800+2%
Boise, ID$2,400 – $5,050$3,700level
Idaho Falls, ID$2,350 – $4,950$3,650−2%

Wages behind the Idaho number

Statewide wages come from BLS's state-level estimates, which blend big cities with small towns and rural areas. 4 trades drive the labor line for this job, and the weighted ratio against the national wage level is 0.98 for Idaho.

For cement masons and concrete finishers (47-2051, weighted 50%) the local median is $27.12 an hour, which is in line with the national $27.41. The middle half of them earn between $22.92 and $29.35 an hour. BLS counts 2,540 of them working in the state, 29.6 for every 10,000 jobs (US: 13.3), so the local bench is deeper than average.

Construction laborers (47-2061), 30% of the weighting: a median of $22.57 an hour, in line with the US median of $22.66. The middle half of them earn between $19.02 and $26.46 an hour. About 10,850 work in the state. That is 126.5 per 10,000 jobs, compared with 70.5 nationally, which suggests plenty of local crews to bid.

For operating engineers and other construction equipment operators (47-2073, weighted 10%) the local median is $29.66 an hour, which is 3% above the national $28.78. The middle half of them earn between $25.28 and $36.25 an hour. BLS counts 4,270 of them working in the state, 49.8 for every 10,000 jobs (US: 30.7), so the local bench is deeper than average.

For carpenters (47-2031, weighted 10%) the local median is $25.00 an hour, which is 14% below the national $29.12. The middle half of them earn between $21.76 and $30.25 an hour. BLS counts 8,380 of them working in the state, 97.7 for every 10,000 jobs (US: 43.1), so the local bench is deeper than average.

A crew paid at the 75th percentile for cement masons and concrete finishers ($29.35 an hour) would add about $65 to the statewide midpoint; one at the 25th percentile ($22.92) would take off about $120. Use that as a rough guide to how far a bid can sit from our midpoint on wages alone.

BLS counts 857,440 jobs across Idaho (May 2025), which is 0.6% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)50%$22.92$27.12$29.35$27.410.99state
Construction laborers (47-2061)30%$19.02$22.57$26.46$22.661.00state
Operating engineers and other construction equipment operators (47-2073)10%$25.28$29.66$36.25$28.781.03state
Carpenters (47-2031)10%$21.76$25.00$30.25$29.120.86state
Blended100%0.98

Optional extras in Idaho

Extras are quoted nationally and then scaled to Idaho by the average of the local wage index (0.98) and goods index (0.96), a factor of 0.97. Tick any of them in the estimator above to add them to your total. Treat these as planning figures: an add-on touches different trades than the main job, so the scaling is an approximation.

Add-on prices
Add-onLocal range
Add rebar reinforcement$390 – $1,150
Remove old concrete first$780 – $2,350

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $3,200 to $4,250 for Idaho is attached.

Take this estimate with you: PDF report, $9

Multi-page report for Idaho: low, typical and high cost, a line-item breakdown of materials and labor by trade, permit notes, the best months to schedule, a quote comparison sheet, red flags, questions for contractors, checklists and every source. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Concrete slab in Idaho: your questions

+How much does it cost to pour a concrete slab in Idaho?

$2,400 to $5,050 for 400 sq ft, using statewide wages and prices. Metro areas inside Idaho can sit above or below that.

+Which city in Idaho is cheapest for concrete slab?

Idaho Falls at about $3,650 (midpoint, 400 sq ft). The priciest is Coeur d'Alene at $3,800.

+Is concrete slab cheaper in Idaho than the US average?

It is 3% cheaper: $3,700 against $3,850 for 400 sq ft at the midpoint.

+What share of the price is labor in Idaho?

About 42% ($1,550). Materials are 52%. Statewide labor for this job is weighted 0.98x the national wage level.

+Does a concrete slab need a permit?

Often yes if it's structural (a garage floor or foundation) and often no for a small at-grade pad. Permit fees run $50-$400 depending on the city (HomeGuide).

+What do cement masons and concrete finishers earn in Idaho?

The BLS statewide median is $27.12 an hour, against $27.41 for the US. The 25th to 75th percentile range is $22.92 to $29.35.

+Where does Idaho rank for concrete slab costs?

32nd most expensive of 51 (the 50 states plus DC) at the midpoint, $3,700 for 400 sq ft. Rank 1 is the costliest.

+What do basic and premium concrete slab work cost in Idaho?

For 400 sq ft, basic work runs $2,400 to $3,450 and premium work $4,000 to $5,050. Basic means: 4-inch broom-finish slab, light mesh, easy truck access. Premium means: 6-inch slab, heavy reinforcement, thick base, pump truck or tight access.

+Does the season matter for concrete slab in Idaho?

Yes where winters or summers are hard. Of the Idaho metros we cover, Coeur d'Alene has the most comfortable months (5 of 12) based on NOAA 1991-2020 normals. Our prices do not change by month, so ask contractors whether they charge more or less in busy and slow seasons.

+What does "add rebar reinforcement" add in Idaho?

$390 to $1,150 for 400 sq ft, from a national range scaled by the statewide wage and goods indexes.