Skip to content
CostLocal

Retaining wall cost in Denver, CO

Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (200 sq ft of wall face)
$7,600 – $14,200
Per sq ft of wall face
$38 – $68.50
before permit
Versus US midpoint
+7%
US $10,300
Rank of 300 metros
#84
1 = most expensive

If you want to build a retaining wall in Denver, plan on $7,600 to $14,200 for 200 sq ft of wall face, all in. Per sq ft of wall face, that is $38 to $68.50 for materials and labor, with the permit on top. The local midpoint runs 7% higher than the national one. Brickmasons and blockmasons earn a median of $36.12 an hour in the Denver area, 21% above the US median of $29.87.

Estimate your retaining wall cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Standard segmental block wall with drainage

Estimated cost for 200 sq ft of wall face in Denver, CO, standard level

$9,600 to $12,200

About $47 to $59.50 per sq ft of wall face before permits. Labor is about 49% of the bill.

Cost breakdown
PartLowHigh
Materials$4,350$6,350
Labor$5,100$5,550
Permits and fees$180$350
Total$9,600$12,200
Save and get a PDF report

Cost breakdown for 200 sq ft of wall face in Denver, CO

Part of the jobLowMidpointHighShare
Materials$2,850$5,350$7,85049%
Labor$4,750$5,300$5,85049%
Permits and fees$55$260$4802%
Total$7,600$10,900$14,200100%

Where the Denver price comes from

We price the labor side from BLS wage data for 3 trades: brickmasons and blockmasons at 50%, construction laborers at 30%, operating engineers and other construction equipment operators at 20%. Weighted together, Denver wages are 1.13 times the national level. Labor makes up about 49% of the midpoint estimate (46% at national prices).

On the materials line, the BEA goods price index for the Denver metro is 101.0 (US = 100). The midpoint materials bill for 200 sq ft of wall face comes to $5,350, compared with $5,300 at national prices. Permit and inspection fees are scaled by the broader index (105.8) and land at $55 to $480.

Denver labor market for retaining wall

Wages are the part of this estimate that changes most from town to town. 3 trades carry the job here, and each is compared with its US median. The weighted result for Denver is 1.13 times the national level.

Brickmasons and blockmasons (47-2021), 50% of the weighting: a median of $36.12 an hour, 21% above the US median of $29.87. The middle half of them earn between $31.29 and $37.06 an hour. About 390 work in the metro. That is 2.4 per 10,000 jobs, compared with 3.4 nationally, so expect fewer local crews to bid.

Construction laborers (47-2061), 30% of the weighting: a median of $23.44 an hour, 3% above the US median of $22.66. The middle half of them earn between $21.48 and $27.44 an hour. About 9,650 work in the metro. That is 60.0 per 10,000 jobs, compared with 70.5 nationally, so the supply of crews looks typical.

For operating engineers and other construction equipment operators (47-2073, weighted 20%) the local median is $30.81 an hour, which is 7% above the national $28.78. The middle half of them earn between $29.32 and $36.58 an hour. BLS counts 5,150 of them working in the area, 32.0 for every 10,000 jobs (US: 30.7), so the local bench is about average.

Quotes come from real crews, not medians. If the brickmasons and blockmasons on your job are paid at the 75th percentile ($37.06 an hour) instead of the median, the labor line grows by about $75. At the 25th percentile ($31.29) it shrinks by about $380. The total moves by 0.7% or 3.5%, so wages alone rarely explain a quote that is far outside our range.

For context on the local economy, BLS counts 1,609,350 jobs in the Denver-Aurora-Centennial area. That makes it the 17th largest of the 300 metros we cover, with 1.03% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Brickmasons and blockmasons (47-2021)50%$31.29$36.12$37.06$29.871.21metro
Construction laborers (47-2061)30%$21.48$23.44$27.44$22.661.03metro
Operating engineers and other construction equipment operators (47-2073)20%$29.32$30.81$36.58$28.781.07metro
Blended100%1.13

What nearby projects cost in Denver

Because every project leans on different trades, Denver's wage level does not move all prices equally. Against the US midpoint, sod installation runs +8% and sprinkler system +2%.

Related projects with local prices
ProjectSizeRangevs. US
French drain60 linear ft$630 – $2,200+6%
Paver patio300 sq ft$3,200 – $5,850+8%
Concrete driveway600 sq ft$3,800 – $9,700+5%
Sod installation1,500 sq ft$1,600 – $3,550+8%
Sprinkler system4,000 sq ft of lawn$4,100 – $10,200+2%
Inground pool450 sq ft$37,700 – $118,000+4%

Is Denver cheap or dear? The local comparison

Of the five closest metros, all are cheaper than Denver. Greeley is the lowest at about $10,100 (midpoint, 200 sq ft of wall face), 80 miles away.

Comparison with nearby areas
AreaRangeMidpointvs. here
Denver, COthis page$7,600 – $14,200$10,900
Colorado Springs, CO45 miles$7,050 – $13,300$10,200−7%
Boulder, CO55 miles$7,250 – $13,500$10,400−5%
Greeley, CO80 miles$6,950 – $13,200$10,100−8%
Fort Collins, CO90 miles$7,200 – $13,500$10,300−6%
Pueblo, CO90 miles$7,000 – $13,200$10,100−7%
Colorado (statewide)$7,200 – $13,600$10,400−5%
United States$7,050 – $13,500$10,300−6%

Across 300 US metros, Denver comes in at #84 from the top. The priciest is Kahului, HI at $13,500; the cheapest is El Paso, TX at $8,850 (midpoints, 200 sq ft of wall face). Statewide, Denver is 5% above the Colorado figure.

Other Colorado metros

Colorado metros compared with Denver
MetroSizeRangeMidpointvs. here
Colorado Springs, CO316,060 jobs$7,050 – $13,300$10,200−7%
Boulder, CO192,390 jobs$7,250 – $13,500$10,400−5%
Fort Collins, CO169,430 jobs$7,200 – $13,500$10,300−6%
Greeley, CO119,540 jobs$6,950 – $13,200$10,100−8%
Grand Junction, CO67,170 jobs$6,950 – $13,100$10,000−8%
Pueblo, CO61,780 jobs$7,000 – $13,200$10,100−7%

Cities with a workforce like Denver's

Big cities and small ones price differently, so here is Denver against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
Riverside, CA1,716,760 jobs$7,750 – $14,400$11,100+1%
San Diego, CA1,538,060 jobs$7,900 – $14,900$11,400+5%
Detroit, MI1,904,530 jobs$7,450 – $13,900$10,700−2%
Tampa, FL1,447,120 jobs$6,550 – $12,600$9,600−12%

Climate in Denver: timing your retaining wall job

We use NOAA's 1991-2020 climate normals for Denver-Stapleton (in the city). These are 30-year monthly averages, not forecasts.

April through June and August through October are the stretches where digging, grading and setting material in the ground runs into the fewest weather problems in Denver (6 of 12 months). January, February, March, November and December have an average overnight low at or below freezing (32°F); July has an average daytime high of 90°F or more.

In January, February, March, November and December the average low is at or below freezing, which means frozen ground and slower digging, compaction and sod or stone placement. NOAA counts about 156 days a year with a low at or below 32°F at this station.

Denver gets about 15 inches of precipitation in a normal year, including roughly 49 inches of snow. The wettest months are May, July and August (2.3 inches in May). Inside the workable window, September and October are the driest, at 1.5 and 1.0 inches. The station averages about 42 days a year at 90°F or above.

Does the season change the price? Probably, but we do not have a sourced seasonal price curve, so the estimator shows a year-round figure and does not adjust by month. When you collect quotes, ask whether scheduling in a slower month gets a better rate.

Monthly normals, Denver-Stapleton (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan47180.5Cold
Feb48190.5Cold
Mar56271.1Cold
Apr63341.7Workable
May72432.3Workable
Jun84531.7Workable
Jul90592.1Hot
Aug88571.8Workable
Sep80481.5Workable
Oct67361.0Workable
Nov55260.7Cold
Dec46180.5Cold

Cost by quality level and size in Denver

Three bands are cut from the same cited range and localized for Denver wages and prices. They overlap on purpose: a good standard job and a modest premium job can cost the same. The grid below prices the same bands at 4 common sizes.

Basic

$7,600 to $10,300

Short block wall, easy access

Standard

$9,600 to $12,200

Standard segmental block wall with drainage

Premium

$11,600 to $14,200

Tall or stone wall, engineered, hard access

Cost by size and quality level
SizeBasicStandardPremium
short garden wall (4x25 ft), 100 sq ft of wall face$3,850 – $5,250$4,900 – $6,300$5,950 – $7,350
20 ft x 4 ft (80 sq ft of wall face)$3,100 – $4,250$3,950 – $5,100$4,800 – $5,950
40 ft x 4 ft (160 sq ft of wall face)$6,100 – $8,250$7,700 – $9,850$9,350 – $11,500
40 ft x 6 ft (240 sq ft of wall face)$9,150 – $12,300$11,500 – $14,600$13,800 – $17,000

Specs and site conditions that change a Denver bid

  • Height

    Walls over 4 feet need engineering, deeper excavation and more skilled labor; many cities require permits over 3-4 feet (HomeGuide).

  • Material

    Block, poured concrete and natural stone are priced differently; concrete and stone walls run higher than the segmental block default.

  • Drainage

    Every wall needs drainage behind it. A French drain adds $10-$85+ per linear foot.

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $9,600 to $12,200 for Denver, CO is attached.

A detailed PDF report of this estimate, $9

The report lays out the retaining wall numbers for Denver, CO line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Retaining wall in Denver: your questions

+How much does it cost to build a retaining wall in Denver?

For 200 sq ft of wall face, expect $7,600 to $14,200 in the Denver area. A standard-spec job lands at $9,600 to $12,200. Small jobs usually cost more per sq ft of wall face and large ones less.

+What is the price per sq ft of wall face for retaining wall in Denver?

About $38 to $68.50 per sq ft of wall face for materials and labor, plus $55 to $480 for the permit if one is needed. The US range is $35 to $65.

+Is retaining wall cheaper in Denver or Colorado Springs?

Colorado Springs is 45 miles away. The midpoint for 200 sq ft of wall face there is $10,200, which is 7% less than Denver ($10,900). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Denver?

About 49% at the midpoint, or $5,300 out of $10,900. Materials are 49% and permits 2%. Nationally, labor is 46%.

+What would 40 ft x 4 ft (160 sq ft of wall face) cost in Denver?

$6,100 to $11,500. Pick a different size in the estimator above to get your own number.

+Does retaining wall need a permit in Denver?

Often, but rules are set by your city or county building office, so call before you hire. Budget $55 to $480 for fees in the Denver area (our national range of $50 to $450 scaled by the local price level).

+Is Denver expensive for retaining wall compared with the rest of Colorado?

Denver is 5% above the Colorado statewide estimate ($10,400 at the midpoint). We cover 7 metros in Colorado; see the state page to compare them.

+What do brickmasons and blockmasons earn in Denver?

The BLS median is $36.12 an hour in the Denver area, compared with $29.87 nationally. The 25th to 75th percentile range is $31.29 to $37.06.

+What do basic and premium retaining wall work cost in Denver?

For 200 sq ft of wall face, basic work runs $7,600 to $10,300 and premium work $11,600 to $14,200. Basic means: short block wall, easy access. Premium means: tall or stone wall, engineered, hard access.

+When is the best time to build a retaining wall in Denver?

Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are April through June and August through October. September and October are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.

Retaining wall near Denver

Retaining wall: all pricesRetaining wall in ColoradoAll projects in DenverColorado cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = 40% of the low installed price and 60% of the high one, since HomeGuide says labor is 40-60% of the total project cost.