Inground pool cost in Medford, OR
Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.
- Typical range (450 sq ft)
- $39,100 – $122,000
- Per sq ft
- $86.50 – $271
- before permit
- Versus US midpoint
- +8%
- US $74,500
- Rank of 300 metros
- #74
- 1 = most expensive
An inground pool in Medford, OR usually costs $39,100 to $122,000 for 450 sq ft. That works out to about $86.50 to $271 per sq ft before permits. Compared with the national midpoint that is $6,150 more. Construction laborers earn a median of $23.72 an hour in the Medford area, 5% above the US median of $22.66.
Estimate your inground pool cost
Pick a size, a quality level and where you live. Prices update as you type.
Estimated cost for 450 sq ft in Medford, OR, standard level
$64,000 to $97,200
About $142 to $215 per sq ft before permits. Labor is about 53% of the bill.
| Part | Low | High |
|---|---|---|
| Materials | $29,700 | $45,200 |
| Labor | $34,200 | $51,800 |
| Permits and fees | $160 | $240 |
| Total | $64,000 | $97,200 |
Cost breakdown for 450 sq ft in Medford, OR
| Part of the job | Low | Midpoint | High | Share |
|---|---|---|---|---|
| Materials | $18,000 | $37,400 | $56,800 | 46% |
| Labor | $21,000 | $43,000 | $65,000 | 53% |
| Permits and fees | $100 | $200 | $300 | 0% |
| Total | $39,100 | $80,600 | $122,000 | 100% |
What is behind the Medford number
Labor is 53% of the midpoint bill here, against 52% nationally. The mix of trades behind this job is construction laborers (40%), operating engineers and other construction equipment operators (30%), brickmasons and blockmasons (20%), plumbers, pipefitters and steamfitters (10%). We weight each trade's local median wage by that share and compare it with the national median. In Medford the blended ratio comes out at 1.11.
Materials are scaled with BEA's regional price parity for goods. Medford is at 105.3 against 100 for the US, so a materials line of $35,600 nationally becomes $37,400 here (midpoint, 450 sq ft). Permits follow the all-items index of 101.4: $100 to $300.
Data note: 20% of the labor weighting for this project uses a statewide median because BLS has no published metro figure for that trade in Medford. The wage table below marks each row.
Medford: what basic, standard and premium work costs
The cited range is split into basic, standard and premium bands, then scaled to Medford. Bands overlap, because plenty of standard jobs cost as much as a light premium one. Sizes run from small pool (400 sq ft) to large (800 sq ft).
Basic
$39,100 to $72,300
Vinyl-liner pool, small size
Standard
$64,000 to $97,200
Fiberglass pool, standard size
Premium
$88,900 to $122,000
Concrete or gunite, large with custom features
| Size | Basic | Standard | Premium |
|---|---|---|---|
| small pool (400 sq ft) | $34,800 – $64,300 | $56,900 – $86,400 | $79,000 – $108,500 |
| average (512 sq ft) | $44,500 – $82,200 | $72,800 – $110,500 | $101,000 – $139,000 |
| large (800 sq ft) | $69,400 – $128,500 | $113,500 – $172,500 | $158,000 – $217,000 |
Medford against nearby metros and the rest of Oregon
Of the five closest metros, none is cheaper than Medford. Eugene comes closest at about $81,000.
| Area | Range | Midpoint | vs. here |
|---|---|---|---|
| Medford, ORthis page | $39,100 – $122,000 | $80,600 | |
| Eugene, OR105 miles | $39,300 – $122,500 | $81,000 | level |
| Redding, CA120 miles | $40,400 – $126,000 | $83,200 | +3% |
| Bend, OR150 miles | $40,100 – $125,500 | $82,700 | +3% |
| Salem, OR175 miles | $41,900 – $130,500 | $86,300 | +7% |
| Chico, CA200 miles | $40,300 – $126,000 | $83,200 | +3% |
| Oregon (statewide) | $40,900 – $128,000 | $84,400 | +5% |
| United States | $36,100 – $113,000 | $74,500 | −8% |
Out of the 300 metros we cover, Medford ranks #74 for the cost of this job (#1 is the most expensive). Statewide, Medford is 4% below the Oregon figure.
Elsewhere in Oregon
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| Portland, OR | 1,208,410 jobs | $42,200 – $132,000 | $87,100 | +8% |
| Salem, OR | 188,620 jobs | $41,900 – $130,500 | $86,300 | +7% |
| Eugene, OR | 157,710 jobs | $39,300 – $122,500 | $81,000 | level |
| Bend, OR | 108,240 jobs | $40,100 – $125,500 | $82,700 | +3% |
Metros of a similar size
Big cities and small ones price differently, so here is Medford against the 4 metros with the closest total employment.
| Metro | Size | Range | Midpoint | vs. here |
|---|---|---|---|---|
| St. George, UT | 90,500 jobs | $34,200 – $107,000 | $70,600 | −12% |
| Florence, SC | 89,060 jobs | $33,000 – $103,000 | $68,100 | −15% |
| Panama City, FL | 90,610 jobs | $32,700 – $102,500 | $67,500 | −16% |
| Bloomington, IL | 88,110 jobs | $42,700 – $133,000 | $88,000 | +9% |
What nearby projects cost in Medford
Jobs that often go together with inground pool are priced below at their usual sizes, using the same Medford wage and price inputs. Compared with national midpoints, retaining wall comes out highest (+10%) and wood deck lowest (+2%); the gap comes from the trades each job uses.
| Project | Size | Range | vs. US |
|---|---|---|---|
| Aluminum fence | 150 linear ft | $3,900 – $11,800 | +3% |
| Paver patio | 300 sq ft | $3,300 – $5,950 | +10% |
| Concrete patio | 300 sq ft | $1,300 – $4,200 | +5% |
| Wood deck | 300 sq ft | $7,700 – $15,400 | +2% |
| French drain | 60 linear ft | $640 – $2,250 | +7% |
| Retaining wall | 200 sq ft of wall face | $7,900 – $14,700 | +10% |
Medford weather and the inground pool calendar
Climate numbers on this page come from NOAA's 1991-2020 U.S. Climate Normals at the nearest suitable station, Medford Rogue Vly Ap (5 miles from the city center). They are 30-year averages, so any one year can run hotter, colder or wetter.
For pouring concrete, the comfortable months in Medford are April through June and September through October: 5 of 12. Outside them, January, February, March, November and December have an average overnight low of 40°F or below, and July and August have an average daytime high of 90°F or more.
The 40°F line is a deliberately cautious stand-in. The American Concrete Institute's cold-weather guide (ACI 306R-16) defines cold-weather concreting around an average daily air temperature below 40°F, which is colder than our test of an average overnight low at or below 40°F, so we flag a few extra shoulder months. In cold weather crews may need heated enclosures, insulating blankets or accelerated mixes, and those measures can raise a quote.
Heat matters for concrete as well. With average highs of 90°F or more in July and August, crews often start early, wet the base and plan for faster set times.
Medford gets about 18 inches of precipitation in a normal year, including roughly 3 inches of snow. The wettest months are January, November and December (3.5 inches in December). Inside the workable window, June and September are the driest, at 0.7 and 0.5 inches. The station averages about 61 days a year at 90°F or above.
We do not adjust the estimate by month, because we have no reliable published data on seasonal pricing. It is still worth asking contractors whether an off-peak start date changes their bid.
| Month | Avg high °F | Avg low °F | Precip (in) | For this job |
|---|---|---|---|---|
| Jan | 48 | 33 | 2.7 | Cold |
| Feb | 54 | 34 | 2.0 | Cold |
| Mar | 59 | 37 | 1.8 | Cold |
| Apr | 65 | 41 | 1.5 | Workable |
| May | 74 | 47 | 1.3 | Workable |
| Jun | 82 | 52 | 0.7 | Workable |
| Jul | 92 | 59 | 0.2 | Hot |
| Aug | 91 | 58 | 0.3 | Hot |
| Sep | 84 | 51 | 0.5 | Workable |
| Oct | 70 | 42 | 1.2 | Workable |
| Nov | 54 | 36 | 2.6 | Cold |
| Dec | 46 | 33 | 3.5 | Cold |
What local crews earn in Medford
The labor line is built from BLS wage data, one trade at a time. This job draws on 4 trades. We compare each trade's local median with the US median, weight the ratios by how much of the job each trade does, and apply the blend to the national labor cost. For Medford the blend is 1.11.
For construction laborers (47-2061, weighted 40%) the local median is $23.72 an hour, which is 5% above the national $22.66. The middle half of them earn between $21.42 and $29.22 an hour. BLS counts 520 of them working in the area, 58.4 for every 10,000 jobs (US: 70.5), so the local bench is thinner than average.
Operating engineers and other construction equipment operators (47-2073), 30% of the weighting: a median of $30.01 an hour, 4% above the US median of $28.78. The middle half of them earn between $26.77 and $37.14 an hour. About 270 work in the metro. That is 30.3 per 10,000 jobs, compared with 30.7 nationally, so the supply of crews looks typical.
Brickmasons and blockmasons (47-2021) carry 20% of the labor weighting. BLS does not publish this trade for the Medford metro, so we used the Oregon statewide median: $38.20 an hour against $29.87 for the US. The middle half of them earn between $31.91 and $47.63 an hour.
Plumbers, pipefitters and steamfitters (47-2152), 10% of the weighting: a median of $37.71 an hour, 23% above the US median of $30.67. The middle half of them earn between $28.53 and $44.88 an hour. About 200 work in the metro. That is 22.5 per 10,000 jobs, compared with 30.0 nationally, so expect fewer local crews to bid.
A quick sensitivity check: moving the lead trade (construction laborers) from the median to the 75th percentile wage adds about $3,750 to the midpoint estimate; the 25th percentile takes off about $1,550. That is a swing of roughly 1.9% to 4.7% of the total, which is useful for judging whether a bid reflects wages or something else, such as scope or margin.
Medford has 89,060 jobs in total (BLS, May 2025), ranking 220th by size among the 300 metros on this site.
| Trade | Weight | 25th pct | Median | 75th pct | US median | Ratio | Level used |
|---|---|---|---|---|---|---|---|
| Construction laborers (47-2061) | 40% | $21.42 | $23.72 | $29.22 | $22.66 | 1.05 | metro |
| Operating engineers and other construction equipment operators (47-2073) | 30% | $26.77 | $30.01 | $37.14 | $28.78 | 1.04 | metro |
| Brickmasons and blockmasons (47-2021) | 20% | $31.91 | $38.20 | $47.63 | $29.87 | 1.28 | state |
| Plumbers, pipefitters and steamfitters (47-2152) | 10% | $28.53 | $37.71 | $44.88 | $30.67 | 1.23 | metro |
| Blended | 100% | 1.11 | |||||
Inground pool: what moves the price in Medford
Pool type
Vinyl pools are $25,000-$65,000, fiberglass $45,000-$100,000, and concrete or gunite $50,000-$120,000 (HomeGuide).
Maintenance
Pool maintenance is $80-$150 a month; concrete pools also need an acid wash every 3-5 years at $300-$1,000.
Permit
A building permit for a pool is $100-$300 and contractors often include it. Many cities add plumbing and electrical permits.
Get 3 local quotes
Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $64,000 to $97,200 for Medford, OR is attached.
Detailed inground pool report for Medford, OR, $9
Multi-page report for Medford, OR: low, typical and high cost, a line-item breakdown of materials and labor by trade, permit notes, the best months to schedule, a quote comparison sheet, red flags, questions for contractors, checklists and every source. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.
Inground pool in Medford: your questions
+How much does it cost to install an inground pool in Medford?
For 450 sq ft, expect $39,100 to $122,000 in the Medford area. A standard-spec job lands at $64,000 to $97,200. Small jobs usually cost more per sq ft and large ones less.
+What is the price per sq ft for inground pool in Medford?
About $86.50 to $271 per sq ft for materials and labor, plus $100 to $300 for the permit if one is needed. The US range is $80 to $250.
+Is inground pool cheaper in Medford or Eugene?
Eugene is 105 miles away. The midpoint for 450 sq ft there is $81,000, which is 0% more than Medford ($80,600). Wage and materials indexes both feed that gap.
+How much of the bill is labor in Medford?
About 53% at the midpoint, or $43,000 out of $80,600. Materials are 46% and permits 0%. Nationally, labor is 52%.
+What would average (512 sq ft) cost in Medford?
$44,500 to $139,000. Pick a different size in the estimator above to get your own number.
+Does inground pool need a permit in Medford?
Often, but rules are set by your city or county building office, so call before you hire. Budget $100 to $300 for fees in the Medford area (our national range of $100 to $300 scaled by the local price level).
+Is Medford expensive for inground pool compared with the rest of Oregon?
Medford is 4% below the Oregon statewide estimate ($84,400 at the midpoint). We cover 5 metros in Oregon; see the state page to compare them.
+What do construction laborers earn in Medford?
The BLS median is $23.72 an hour in the Medford area, compared with $22.66 nationally. The 25th to 75th percentile range is $21.42 to $29.22.
+What do basic and premium inground pool work cost in Medford?
For 450 sq ft, basic work runs $39,100 to $72,300 and premium work $88,900 to $122,000. Basic means: vinyl-liner pool, small size. Premium means: concrete or gunite, large with custom features.
+When is the best time to install an inground pool in Medford?
Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are April through June and September through October. June and September are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.
Inground pool near Medford
Where these numbers come from
Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.
- HomeGuide: How Much Does An Inground Pool Cost? (2026) (accessed November 4, 2026)
- Cost to Renovate: Renovation Labor Report 2026: Where the Money Goes (accessed November 4, 2026)
- BLS Occupational Employment and Wage Statistics, May 2025
- BEA Regional Price Parities, 2024
- NOAA NCEI U.S. Climate Normals, 1991-2020
Note on derived figures: Materials = 48% of the installed price, from Cost to Renovate's mid-range 'Outdoor Living' category split. It is a category average, not a pool-specific one, so read the pool materials line loosely.