Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (300 sq ft)
$1,250 – $4,000
Per sq ft
$3.95 – $12
before permit
Versus US midpoint
Level
US $2,650
Rank of 300 metros
#132
1 = most expensive

Local price for a concrete patio in the Fort Collins area: $1,250 to $4,000 for 300 sq ft. The low end is a basic job on easy ground; the high end is a premium spec with harder access. The midpoint lands close to the US figure. Building materials run about 4% below the US average here (BEA goods price index 96.1).

Estimate your concrete patio cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Colored or stained, saw-cut joints, minor grading

Add-ons

Estimated cost for 300 sq ft in Fort Collins, CO, standard level

$2,050 to $3,150

About $6.35 to $9.60 per sq ft before permits. Labor is about 53% of the bill.

Cost breakdown
PartLowHigh
Materials$890$1,100
Labor$1,000$1,750
Permits and fees$160$300
Total$2,050$3,150
Save and get a PDF report

Cost breakdown for 300 sq ft in Fort Collins, CO

Part of the jobLowMidpointHighShare
Materials$720$1,000$1,30039%
Labor$460$1,400$2,30053%
Permits and fees$50$230$4009%
Total$1,250$2,600$4,000100%

Why Fort Collins prices look the way they do

Labor is 53% of the midpoint bill here, against 51% nationally. The mix of trades behind this job is cement masons and concrete finishers (50%), construction laborers (30%), carpenters (10%), operating engineers and other construction equipment operators (10%). We weight each trade's local median wage by that share and compare it with the national median. In Fort Collins the blended ratio comes out at 1.02.

Materials are scaled with BEA's regional price parity for goods. Fort Collins is at 96.1 against 100 for the US, so a materials line of $1,050 nationally becomes $1,000 here (midpoint, 300 sq ft). Permits follow the all-items index of 101.1: $50 to $400.

Cost by quality level and size in Fort Collins

The cited range is split into basic, standard and premium bands, then scaled to Fort Collins. Bands overlap, because plenty of standard jobs cost as much as a light premium one. Sizes run from 10x10 (100 sq ft) to 20x20 (400 sq ft).

Basic

$1,250 to $2,350

Plain gray slab, broom finish, flat yard

Standard

$2,050 to $3,150

Colored or stained, saw-cut joints, minor grading

Premium

$2,900 to $4,000

Exposed aggregate or heavy decorative finish, drainage work

Cost by size and quality level
SizeBasicStandardPremium
10x10 (100 sq ft)$440 – $910$790 – $1,250$1,150 – $1,600
12x16 (192 sq ft)$810 – $1,550$1,400 – $2,150$1,950 – $2,700
20x20 (400 sq ft)$1,650 – $3,050$2,700 – $4,150$3,750 – $5,200

The best months for concrete patio in Fort Collins

Climate numbers on this page come from NOAA's 1991-2020 U.S. Climate Normals at the nearest suitable station, Ft Collins (5 miles from the city center). They are 30-year averages, so any one year can run hotter, colder or wetter.

For pouring concrete, the comfortable months in Fort Collins are May through September: 5 of 12. Outside them, January, February, March, April, October, November and December have an average overnight low of 40°F or below.

The 40°F line is a deliberately cautious stand-in. The American Concrete Institute's cold-weather guide (ACI 306R-16) defines cold-weather concreting around an average daily air temperature below 40°F, which is colder than our test of an average overnight low at or below 40°F, so we flag a few extra shoulder months. In cold weather crews may need heated enclosures, insulating blankets or accelerated mixes, and those measures can raise a quote.

Fort Collins gets about 16 inches of precipitation in a normal year, including roughly 51 inches of snow. The wettest months are April, May and June (2.7 inches in May). Inside the workable window, August and September are the driest, at 1.4 and 1.4 inches. The station averages about 29 days a year at 90°F or above.

We do not adjust the estimate by month, because we have no reliable published data on seasonal pricing. It is still worth asking contractors whether an off-peak start date changes their bid.

Monthly normals, Ft Collins (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan45180.4Cold
Feb47210.5Cold
Mar56291.3Cold
Apr63352.1Cold
May71442.7Workable
Jun82531.9Workable
Jul87591.6Workable
Aug85571.4Workable
Sep77481.4Workable
Oct64361.3Cold
Nov53260.7Cold
Dec44180.5Cold

Extras that change the Fort Collins total

Add-ons start from national price ranges and are scaled by 0.99 for Fort Collins, which is the average of the area's wage index (1.02) and goods price index (0.96). The estimator above can add them to your total.

Add-on prices
Add-onLocal range
Add an acid or water-based stain$890 – $3,000

Related projects, priced for Fort Collins

Jobs that often go together with concrete patio are priced below at their usual sizes, using the same Fort Collins wage and price inputs. Compared with national midpoints, paver patio comes out highest (+2%) and wood deck lowest (−3%); the gap comes from the trades each job uses.

Related projects with local prices
ProjectSizeRangevs. US
Concrete slab400 sq ft$2,450 – $5,150−1%
Stamped concrete400 sq ft$3,200 – $7,950level
Paver patio300 sq ft$3,050 – $5,550+2%
Wood deck300 sq ft$7,300 – $14,600−3%
Concrete driveway600 sq ft$3,650 – $9,250level
Asphalt driveway600 sq ft$3,050 – $7,550+2%

Who does the work: Fort Collins trade wages

The labor line is built from BLS wage data, one trade at a time. This job draws on 4 trades. We compare each trade's local median with the US median, weight the ratios by how much of the job each trade does, and apply the blend to the national labor cost. For Fort Collins the blend is 1.02.

Cement masons and concrete finishers (47-2051), 50% of the weighting: a median of $28.31 an hour, 3% above the US median of $27.41. The middle half of them earn between $23.15 and $30.36 an hour. About 320 work in the metro. That is 18.9 per 10,000 jobs, compared with 13.3 nationally, which suggests plenty of local crews to bid.

For construction laborers (47-2061, weighted 30%) the local median is $22.86 an hour, which is in line with the national $22.66. The middle half of them earn between $20.83 and $27.15 an hour. BLS counts 930 of them working in the area, 54.9 for every 10,000 jobs (US: 70.5), so the local bench is thinner than average.

Carpenters (47-2031), 10% of the weighting: a median of $28.04 an hour, 4% below the US median of $29.12. The middle half of them earn between $23.36 and $30.74 an hour. About 510 work in the metro. That is 30.1 per 10,000 jobs, compared with 43.1 nationally, so expect fewer local crews to bid.

Operating engineers and other construction equipment operators (47-2073), 10% of the weighting: a median of $31.08 an hour, 8% above the US median of $28.78. The middle half of them earn between $29.33 and $35.64 an hour. About 600 work in the metro. That is 35.4 per 10,000 jobs, compared with 30.7 nationally, which suggests plenty of local crews to bid.

A quick sensitivity check: moving the lead trade (cement masons and concrete finishers) from the median to the 75th percentile wage adds about $50 to the midpoint estimate; the 25th percentile takes off about $130. That is a swing of roughly 4.9% to 1.9% of the total, which is useful for judging whether a bid reflects wages or something else, such as scope or margin.

Fort Collins-Loveland has 169,430 jobs in total (BLS, May 2025), ranking 138th by size among the 300 metros on this site.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Cement masons and concrete finishers (47-2051)50%$23.15$28.31$30.36$27.411.03metro
Construction laborers (47-2061)30%$20.83$22.86$27.15$22.661.01metro
Carpenters (47-2031)10%$23.36$28.04$30.74$29.120.96metro
Operating engineers and other construction equipment operators (47-2073)10%$29.33$31.08$35.64$28.781.08metro
Blended100%1.02

Is Fort Collins cheap or dear? The local comparison

Of the five closest metros, 3 are cheaper than Fort Collins. Greeley is the lowest at about $2,600 (midpoint, 300 sq ft), 60 miles away.

Comparison with nearby areas
AreaRangeMidpointvs. here
Fort Collins, COthis page$1,250 – $4,000$2,600
Boulder, CO40 miles$1,250 – $4,100$2,650+2%
Greeley, CO60 miles$1,200 – $3,950$2,600−1%
Cheyenne, WY60 miles$1,250 – $4,000$2,600−1%
Denver, CO90 miles$1,300 – $4,200$2,750+5%
Colorado Springs, CO135 miles$1,250 – $4,000$2,600level
Colorado (statewide)$1,250 – $4,100$2,700+2%
United States$1,250 – $4,000$2,650level

Out of the 300 metros we cover, Fort Collins ranks #132 for the cost of this job (#1 is the most expensive). Statewide, Fort Collins is 2% below the Colorado figure.

Elsewhere in Colorado

Colorado metros compared with Fort Collins
MetroSizeRangeMidpointvs. here
Denver, CO1,609,350 jobs$1,300 – $4,200$2,750+5%
Colorado Springs, CO316,060 jobs$1,250 – $4,000$2,600level
Boulder, CO192,390 jobs$1,250 – $4,100$2,650+2%
Greeley, CO119,540 jobs$1,200 – $3,950$2,600−1%
Grand Junction, CO67,170 jobs$1,200 – $3,850$2,550−3%
Pueblo, CO61,780 jobs$1,200 – $3,850$2,550−3%

Metros of a similar size

Big cities and small ones price differently, so here is Fort Collins against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
Port St. Lucie, FL170,820 jobs$1,150 – $3,650$2,400−9%
Atlantic City, NJ168,700 jobs$1,300 – $4,300$2,800+7%
Visalia, CA171,140 jobs$1,300 – $4,100$2,700+3%
Lubbock, TX166,780 jobs$1,100 – $3,450$2,300−13%

Why two Fort Collins quotes can differ

  • Site prep

    Excavation, forms and a gravel base are the unglamorous part of the bill and vary most with soil and slope.

  • Size

    Small patios carry fixed costs for forms and mobilization, so the per-square-foot price drops as the patio gets bigger.

  • Permit

    Permits run $50-$400 where required. Many cities don't require one for a small at-grade patio.

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $2,050 to $3,150 for Fort Collins, CO is attached.

Detailed concrete patio report for Fort Collins, CO, $9

The report lays out the concrete patio numbers for Fort Collins, CO line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Concrete patio in Fort Collins: your questions

+How much does it cost to pour a concrete patio in Fort Collins?

For 300 sq ft, expect $1,250 to $4,000 in the Fort Collins area. A standard-spec job lands at $2,050 to $3,150. Small jobs usually cost more per sq ft and large ones less.

+What is the price per sq ft for concrete patio in Fort Collins?

About $3.95 to $12 per sq ft for materials and labor, plus $50 to $400 for the permit if one is needed. The US range is $4 to $12.

+Is concrete patio cheaper in Fort Collins or Boulder?

Boulder is 40 miles away. The midpoint for 300 sq ft there is $2,650, which is 2% more than Fort Collins ($2,600). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Fort Collins?

About 53% at the midpoint, or $1,400 out of $2,600. Materials are 39% and permits 9%. Nationally, labor is 51%.

+What would 12x16 (192 sq ft) cost in Fort Collins?

$810 to $2,700. Pick a different size in the estimator above to get your own number.

+Does concrete patio need a permit in Fort Collins?

Often, but rules are set by your city or county building office, so call before you hire. Budget $50 to $400 for fees in the Fort Collins area (our national range of $50 to $400 scaled by the local price level).

+Is Fort Collins expensive for concrete patio compared with the rest of Colorado?

Fort Collins is 2% below the Colorado statewide estimate ($2,700 at the midpoint). We cover 7 metros in Colorado; see the state page to compare them.

+What do cement masons and concrete finishers earn in Fort Collins?

The BLS median is $28.31 an hour in the Fort Collins area, compared with $27.41 nationally. The 25th to 75th percentile range is $23.15 to $30.36.

+What do basic and premium concrete patio work cost in Fort Collins?

For 300 sq ft, basic work runs $1,250 to $2,350 and premium work $2,900 to $4,000. Basic means: plain gray slab, broom finish, flat yard. Premium means: exposed aggregate or heavy decorative finish, drainage work.

+When is the best time to pour a concrete patio in Fort Collins?

Based on NOAA 1991-2020 normals, the comfortable months for this kind of work are May through September. August and September are typically the driest of those months. Local contractors' schedules matter as much as the weather, so book early for the busy months.

+What does "add an acid or water-based stain" add in Fort Collins?

$890 to $3,000 for 300 sq ft, from a national range scaled by the local wage and goods indexes.

Concrete patio near Fort Collins

Concrete patio: all pricesConcrete patio in ColoradoAll projects in Fort CollinsColorado cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = SimplyWise's sample 200 sq ft broom-finish patio line ($500-$900 in materials) divided by 200 sq ft.