Asphalt driveway cost in Vermont

Statewide estimate from BLS wages and BEA prices. Reviewed Nov 4, 2026.

Statewide range (600 sq ft)
$3,000 – $7,350
Per sq ft
$4.95 – $12
before permit
Versus US midpoint
−1%
US $5,250
Metros covered
1

What does it cost to pave a driveway in Vermont? Plan on $3,000 to $7,350 for 600 sq ft. Wages (1.02x the US blend), materials (price index 97.3) and permit costs (98.0) put the state below the national midpoint by 1%.

Vermont has one metro in our dataset, Burlington, so the statewide and metro figures are close. The state figure uses BLS statewide wages, which include rural areas.

Estimate your asphalt driveway cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Full new driveway: base, 2-3 in of hot mix, edging

Add-ons

Estimated cost for 600 sq ft in Vermont (statewide), standard level

$4,300 to $6,050

About $7.05 to $9.80 per sq ft before permits. Labor is about 42% of the bill.

Cost breakdown
PartLowHigh
Materials$2,500$3,250
Labor$1,700$2,600
Permits and fees$95$150
Total$4,300$6,050
Save and get a PDF report

Cost breakdown for 600 sq ft in Vermont

Part of the jobLowMidpointHighShare
Materials$1,950$2,900$3,85056%
Labor$1,050$2,150$3,30042%
Permits and fees$50$120$2002%
Total$3,000$5,150$7,350100%

Weather windows across Vermont

Weather decides when digging and ground work can happen, and Vermont is not uniform. The table uses NOAA's 1991-2020 climate normals from the weather station nearest each metro we cover, and counts the months that are neither cold nor hot enough to complicate the job.

Burlington has 7 comfortable months (April through October), with about 38 inches of precipitation a year.

We do not adjust prices by month, because we have no reliable published data on seasonal pricing. Timing is still worth raising when you collect bids.

Climate by metro (NOAA 1991-2020 normals)
MetroJan avg low °FJul avg high °FPrecip (in/yr)Comfortable months
Burlington1382387: April through October

Add-ons priced for Vermont

Add-ons start from national price ranges and are scaled by 0.99 for Vermont, which is the average of the area's wage index (1.02) and goods price index (0.97). The estimator above can add them to your total.

Add-on prices
Add-onLocal range
Add a sealcoat$600 – $1,200

Other Vermont jobs that often go with asphalt driveway

Each project weights the trades differently, so Vermont's wage level does not push every price by the same amount. Compared with the US midpoint, concrete driveway is +2% and gravel driveway −1%.

Related projects with local prices
ProjectSizeRangevs. US
Concrete driveway600 sq ft$3,700 – $9,450+2%
Gravel driveway1,000 sq ft$2,500 – $10,100−1%
Paver patio300 sq ft$3,050 – $5,500+1%
French drain60 linear ft$600 – $2,100−1%
Concrete slab400 sq ft$2,450 – $5,200level
Concrete patio300 sq ft$1,250 – $4,050+1%

What paving, surfacing and tamping equipment operators and the other trades earn in Vermont

Vermont's labor line is priced from 3 trades, each compared with its US median wage. After weighting by each trade's share of the work, the state comes out at 1.02 times the national level.

Paving, surfacing and tamping equipment operators (47-2071), 40% of the weighting: a median of $26.36 an hour, in line with the US median of $25.64. The middle half of them earn between $24.00 and $29.83 an hour. About 70 work in the state. That is 2.3 per 10,000 jobs, compared with 2.7 nationally, so the supply of crews looks typical.

For construction laborers (47-2061, weighted 30%) the local median is $23.36 an hour, which is 3% above the national $22.66. The middle half of them earn between $22.49 and $27.94 an hour. BLS counts 1,430 of them working in the state, 47.1 for every 10,000 jobs (US: 70.5), so the local bench is thinner than average.

Operating engineers and other construction equipment operators (47-2073), 30% of the weighting: a median of $28.30 an hour, in line with the US median of $28.78. The middle half of them earn between $25.37 and $30.62 an hour. About 1,280 work in the state. That is 42.1 per 10,000 jobs, compared with 30.7 nationally, which suggests plenty of local crews to bid.

A crew paid at the 75th percentile for paving, surfacing and tamping equipment operators ($29.83 an hour) would add about $120 to the statewide midpoint; one at the 25th percentile ($24.00) would take off about $80. Use that as a rough guide to how far a bid can sit from our midpoint on wages alone.

BLS counts 303,890 jobs across Vermont (May 2025), which is 0.2% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Paving, surfacing and tamping equipment operators (47-2071)40%$24.00$26.36$29.83$25.641.03state
Construction laborers (47-2061)30%$22.49$23.36$27.94$22.661.03state
Operating engineers and other construction equipment operators (47-2073)30%$25.37$28.30$30.62$28.780.98state
Blended100%1.02

Vermont versus the states around it

Vermont ranks 26 of 51 (the 50 states plus DC) for asphalt driveway, where 1 is the most expensive. The costliest is Hawaii at $7,500 and the cheapest Mississippi at $4,600, both for 600 sq ft at the midpoint. Vermont sits at $5,150. The five states closest by workforce center are listed below.

States near Vermont, same project and size
StateDistanceRangeMidpointvs. here
New Hampshire140 miles away$3,100 – $7,650$5,400+4%
Maine150 miles away$3,000 – $7,300$5,150−1%
Massachusetts180 miles away$3,300 – $8,150$5,700+11%
Connecticut220 miles away$3,350 – $8,450$5,900+14%
Rhode Island220 miles away$3,150 – $7,800$5,500+6%

Asphalt driveway cost by metro in Vermont

Vermont has one metro in our dataset, Burlington, so the statewide and metro figures are close. The state figure uses BLS statewide wages, which include rural areas. Each row prices the default size with that metro's own BLS wages and BEA price levels, so the gap between rows is real local variation rather than a flat markup.

MetroRange (600 sq ft)Midpointvs. state
Burlington, VT$3,050 – $7,400$5,200+1%

Why two Vermont quotes can differ

  • New versus overlay

    Resurfacing an existing driveway runs $3-$7 per sq ft; a full new driveway runs $5-$12+ (HomeGuide). Tearing out and replacing one is higher still.

  • Base work

    Four to eight inches of compacted aggregate under the asphalt is where cheap quotes cut corners. Base typically runs $1-$3 per sq ft.

  • Small jobs cost more per foot

    Paving crews move a paver, roller and trucks to your address, so a 400 sq ft driveway carries more mobilization per square foot than a 1,000 sq ft one.

  • Hot-mix price

    Hot-mix asphalt is $100-$200 per ton delivered and moves with oil prices (PaveGauge).

  • Sealcoating

    Sealing is $1-$2 per sq ft and is a maintenance cost, not part of the install.

Basic, standard or premium: Vermont prices

Bands overlap on purpose, since a good standard job can cost as much as a light premium one. Below are the three bands for the default size, then a grid from 1-car (12x20), 240 sq ft to long rural (10x100), 1,000 sq ft.

Basic

$3,000 to $4,750

New topcoat over a sound base, flat lot

Standard

$4,300 to $6,050

Full new driveway: base, 2-3 in of hot mix, edging

Premium

$5,600 to $7,350

Full tear-out and rebuild, drainage work, heavy-duty depth

Cost by size and quality level
SizeBasicStandardPremium
1-car (12x20), 240 sq ft$1,250 – $1,950$1,800 – $2,500$2,350 – $3,050
20x20 (400 sq ft)$2,000 – $3,200$2,900 – $4,100$3,800 – $4,950
2-car (20x30), 600 sq ft$3,000 – $4,750$4,300 – $6,050$5,600 – $7,350
long rural (10x100), 1,000 sq ft$5,000 – $7,850$7,100 – $9,950$9,250 – $12,100

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $4,300 to $6,050 for Vermont is attached.

Detailed asphalt driveway report for Vermont, $9

The report lays out the asphalt driveway numbers for Vermont line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

Asphalt driveway in Vermont: your questions

+How much does it cost to pave a driveway in Vermont?

$3,000 to $7,350 for 600 sq ft, using statewide wages and prices. Metro areas inside Vermont can sit above or below that.

+Which city in Vermont is cheapest for asphalt driveway?

Burlington at about $5,200 (midpoint, 600 sq ft).

+Is asphalt driveway cheaper in Vermont than the US average?

It is 1% cheaper: $5,150 against $5,250 for 600 sq ft at the midpoint.

+What share of the price is labor in Vermont?

About 42% ($2,150). Materials are 56%. Statewide labor for this job is weighted 1.02x the national wage level.

+What do paving, surfacing and tamping equipment operators earn in Vermont?

The BLS statewide median is $26.36 an hour, against $25.64 for the US. The 25th to 75th percentile range is $24.00 to $29.83.

+Where does Vermont rank for asphalt driveway costs?

26th most expensive of 51 (the 50 states plus DC) at the midpoint, $5,150 for 600 sq ft. Rank 1 is the costliest.

+What do basic and premium asphalt driveway work cost in Vermont?

For 600 sq ft, basic work runs $3,000 to $4,750 and premium work $5,600 to $7,350. Basic means: new topcoat over a sound base, flat lot. Premium means: full tear-out and rebuild, drainage work, heavy-duty depth.

+Does the season matter for asphalt driveway in Vermont?

Yes where winters or summers are hard. Of the Vermont metros we cover, Burlington has the most comfortable months (7 of 12) based on NOAA 1991-2020 normals. Our prices do not change by month, so ask contractors whether they charge more or less in busy and slow seasons.

+What does "add a sealcoat" add in Vermont?

$600 to $1,200 for 600 sq ft, from a national range scaled by the statewide wage and goods indexes.

Asphalt driveway by city in Vermont

Asphalt driveway: all pricesVermont cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = hot-mix asphalt ($2.30-$3.60/sq ft at 3 in) plus aggregate base ($1-$3/sq ft) from PaveGauge's component table.