Skip to content
CostLocal

French drain cost in Myrtle Beach, SC

Local estimate from BLS wage data and BEA price levels. Reviewed Nov 4, 2026.

Typical range (60 linear ft)
$530 – $1,850
Per linear ft
$8.85 – $31
before permit
Versus US midpoint
−11%
US $1,350
Rank of 300 metros
#268
1 = most expensive

Myrtle Beach homeowners pay roughly $530 to $1,850 to install a French drain at 60 linear ft, or $8.85 to $31 per linear ft (permit not included). Against the US midpoint, Myrtle Beach is 11% lower. Construction laborers earn a median of $18.37 an hour in the Myrtle Beach area, 19% below the US median of $22.66.

Estimate your french drain cost

Pick a size, a quality level and where you live. Prices update as you type.

Quality level

Standard drain with fabric, gravel and a pop-up outlet

Estimated cost for 60 linear ft in Myrtle Beach, SC, standard level

$930 to $1,450

About $15.50 to $24.50 per linear ft before permits. Labor is about 48% of the bill.

Cost breakdown
PartLowHigh
Materials$490$760
Labor$450$700
Permits and fees$0$0
Total$930$1,450
Save and get a PDF report

Cost breakdown for 60 linear ft in Myrtle Beach, SC

Part of the jobLowMidpointHighShare
Materials$280$620$97052%
Labor$250$570$89048%
Permits and fees$0$0$00%
Total$530$1,200$1,850100%

What is behind the Myrtle Beach number

The wage side of the estimate leans on construction laborers, who do 50% of the hours on a typical job. Their local median is $18.37 an hour. Add the other trades involved and the blended wage index for Myrtle Beach is 0.82 (US = 1.00), which puts labor at 48% of the total.

On the materials line, the BEA goods price index for the Myrtle Beach metro is 96.3 (US = 100). The midpoint materials bill for 60 linear ft comes to $620, compared with $650 at national prices. Permit and inspection fees are scaled by the broader index (93.6) and land at $0 to $0.

Myrtle Beach against nearby metros and the rest of South Carolina

Of the five closest metros, none is cheaper than Myrtle Beach. Florence comes closest at about $1,250.

Comparison with nearby areas
AreaRangeMidpointvs. here
Myrtle Beach, SCthis page$530 – $1,850$1,200
Florence, SC50 miles$550 – $1,950$1,250+3%
Wilmington, NC60 miles$560 – $2,000$1,250+6%
Fayetteville, NC80 miles$560 – $1,950$1,250+5%
Charleston, SC85 miles$560 – $1,950$1,250+6%
Columbia, SC120 miles$550 – $1,950$1,250+3%
South Carolina (statewide)$550 – $1,950$1,250+4%
United States$600 – $2,100$1,350+13%

Across 300 US metros, Myrtle Beach comes in at #268 from the top. The priciest is San Francisco, CA at $1,900; the cheapest is McAllen, TX at $1,100 (midpoints, 60 linear ft). Statewide, Myrtle Beach is 4% below the South Carolina figure.

Other South Carolina metros

South Carolina metros compared with Myrtle Beach
MetroSizeRangeMidpointvs. here
Greenville, SC434,900 jobs$560 – $1,950$1,250+5%
Columbia, SC394,200 jobs$550 – $1,950$1,250+3%
Charleston, SC394,170 jobs$560 – $1,950$1,250+6%
Spartanburg, SC165,150 jobs$550 – $1,950$1,250+4%
Florence, SC89,060 jobs$550 – $1,950$1,250+3%
Hilton Head, SC81,920 jobs$560 – $2,000$1,250+6%

Cities with a workforce like Myrtle Beach's

Big cities and small ones price differently, so here is Myrtle Beach against the 4 metros with the closest total employment.

Metros closest to this one by total employment
MetroSizeRangeMidpointvs. here
Fargo, ND148,660 jobs$600 – $2,100$1,350+12%
Vallejo, CA144,130 jobs$760 – $2,650$1,700+42%
Killeen, TX150,580 jobs$530 – $1,850$1,200−1%
Huntington, WV140,740 jobs$590 – $2,050$1,300+10%

Planning more than one job in Myrtle Beach?

Because every project leans on different trades, Myrtle Beach's wage level does not move all prices equally. Against the US midpoint, sod installation runs −8% and sprinkler system −13%.

Related projects with local prices
ProjectSizeRangevs. US
Retaining wall200 sq ft of wall face$6,000 – $12,000−12%
Gravel driveway1,000 sq ft$2,200 – $9,000−12%
Sod installation1,500 sq ft$1,350 – $3,000−8%
Concrete slab400 sq ft$2,150 – $4,700−11%
Sprinkler system4,000 sq ft of lawn$3,500 – $8,700−13%
Inground pool450 sq ft$31,500 – $98,400−13%

When to schedule French drain in Myrtle Beach

We use NOAA's 1991-2020 climate normals for Myrtle Beach (5 miles from the city center). These are 30-year monthly averages, not forecasts.

Weather is not a serious constraint for digging, grading and setting material in the ground in Myrtle Beach: no month in the averages is cold enough (an average overnight low at or below freezing (32°F)) or hot enough (an average daytime high of 90°F or more) to rule it out, so the workable window is all year.

Myrtle Beach gets about 54 inches of precipitation in a normal year. The wettest months are July, August and September (6.8 inches in September). The station averages about 22 days a year at 90°F or above.

Does the season change the price? Probably, but we do not have a sourced seasonal price curve, so the estimator shows a year-round figure and does not adjust by month. When you collect quotes, ask whether scheduling in a slower month gets a better rate.

Monthly normals, Myrtle Beach (NOAA, 1991-2020)
MonthAvg high °FAvg low °FPrecip (in)For this job
Jan56343.4Workable
Feb58363.8Workable
Mar64423.7Workable
Apr72513.4Workable
May79603.8Workable
Jun85684.8Workable
Jul87726.6Workable
Aug87706.3Workable
Sep83656.8Workable
Oct76544.1Workable
Nov66423.1Workable
Dec59363.8Workable

French drain: what moves the price in Myrtle Beach

  • Exterior versus interior

    A shallow exterior French drain is $10-$35 per linear foot; an interior basement drain is $40-$85 per foot, or $4,000-$17,000 installed (HomeGuide).

  • Where the water goes

    A sump pump adds $500-$1,800 and a dry well $50-$3,000+. Discharging to a storm drain can mean extra permit fees.

  • Depth and soil

    Rocky or clay soil and long trenches raise excavation time.

Myrtle Beach: what basic, standard and premium work costs

Three bands are cut from the same cited range and localized for Myrtle Beach wages and prices. They overlap on purpose: a good standard job and a modest premium job can cost the same. The grid below prices the same bands at 3 common sizes.

Basic

$530 to $1,050

Shallow yard drain, easy digging

Standard

$930 to $1,450

Standard drain with fabric, gravel and a pop-up outlet

Premium

$1,350 to $1,850

Deep or long drain, hard soil, dry well or sump discharge

Cost by size and quality level
SizeBasicStandardPremium
short run (30 linear ft)$270 – $530$470 – $730$670 – $930
side yard (60 linear ft)$530 – $1,050$930 – $1,450$1,350 – $1,850
long run (120 linear ft)$1,050 – $2,150$1,850 – $2,950$2,650 – $3,700

Local wages behind the labor line

Wages are the part of this estimate that changes most from town to town. 3 trades carry the job here, and each is compared with its US median. The weighted result for Myrtle Beach is 0.82 times the national level.

Construction laborers (47-2061), 50% of the weighting: a median of $18.37 an hour, 19% below the US median of $22.66. The middle half of them earn between $17.32 and $22.65 an hour. About 1,440 work in the metro. That is 98.5 per 10,000 jobs, compared with 70.5 nationally, which suggests plenty of local crews to bid.

For operating engineers and other construction equipment operators (47-2073, weighted 30%) the local median is $22.59 an hour, which is 22% below the national $28.78. The middle half of them earn between $19.93 and $23.83 an hour. BLS counts 980 of them working in the area, 67.0 for every 10,000 jobs (US: 30.7), so the local bench is deeper than average.

Pipelayers (47-2151), 20% of the weighting: a median of $20.65 an hour, 12% below the US median of $23.56. The middle half of them earn between $18.73 and $22.10 an hour. About 60 work in the metro. That is 4.1 per 10,000 jobs, compared with 2.1 nationally, which suggests plenty of local crews to bid.

Quotes come from real crews, not medians. If the construction laborers on your job are paid at the 75th percentile ($22.65 an hour) instead of the median, the labor line grows by about $65. At the 25th percentile ($17.32) it shrinks by about $15. The total moves by 5.5% or 1.4%, so wages alone rarely explain a quote that is far outside our range.

For context on the local economy, BLS counts 146,260 jobs in the Myrtle Beach-Conway-North Myrtle Beach area. That makes it the 157th largest of the 300 metros we cover, with 0.09% of US employment.

Median hourly wages behind the labor line (BLS OEWS, May 2025)
TradeWeight25th pctMedian75th pctUS medianRatioLevel used
Construction laborers (47-2061)50%$17.32$18.37$22.65$22.660.81metro
Operating engineers and other construction equipment operators (47-2073)30%$19.93$22.59$23.83$28.780.78metro
Pipelayers (47-2151)20%$18.73$20.65$22.10$23.560.88metro
Blended100%0.82

Get 3 local quotes

Tell us about the job and we will try to connect you with up to three local contractors for written quotes. It is free and you are under no obligation to hire. Your estimate of $930 to $1,450 for Myrtle Beach, SC is attached.

Take this estimate with you: PDF report, $9

The report lays out the french drain numbers for Myrtle Beach, SC line by line, with the local wage and price inputs, permit and timing notes, a quote comparison sheet and the full method. Save your estimate above, preview page 1 free, and unlock the full report for $9 one-time, or get every report with CostLocal Pro.

French drain in Myrtle Beach: your questions

+How much does it cost to install a French drain in Myrtle Beach?

For 60 linear ft, expect $530 to $1,850 in the Myrtle Beach area. A standard-spec job lands at $930 to $1,450. Small jobs usually cost more per linear ft and large ones less.

+What is the price per linear ft for French drain in Myrtle Beach?

About $8.85 to $31 per linear ft for materials and labor, plus $0 to $0 for the permit if one is needed. The US range is $10 to $35.

+Is French drain cheaper in Myrtle Beach or Florence?

Florence is 50 miles away. The midpoint for 60 linear ft there is $1,250, which is 3% more than Myrtle Beach ($1,200). Wage and materials indexes both feed that gap.

+How much of the bill is labor in Myrtle Beach?

About 48% at the midpoint, or $570 out of $1,200. Materials are 52% and permits 0%. Nationally, labor is 52%.

+What would side yard (60 linear ft) cost in Myrtle Beach?

$530 to $1,850. Pick a different size in the estimator above to get your own number.

+Does French drain need a permit in Myrtle Beach?

Often, but rules are set by your city or county building office, so call before you hire. Budget $0 to $0 for fees in the Myrtle Beach area (our national range of $0 to $0 scaled by the local price level).

+Is Myrtle Beach expensive for French drain compared with the rest of South Carolina?

Myrtle Beach is 4% below the South Carolina statewide estimate ($1,250 at the midpoint). We cover 7 metros in South Carolina; see the state page to compare them.

+What do construction laborers earn in Myrtle Beach?

The BLS median is $18.37 an hour in the Myrtle Beach area, compared with $22.66 nationally. The 25th to 75th percentile range is $17.32 to $22.65.

+What do basic and premium French drain work cost in Myrtle Beach?

For 60 linear ft, basic work runs $530 to $1,050 and premium work $1,350 to $1,850. Basic means: shallow yard drain, easy digging. Premium means: deep or long drain, hard soil, dry well or sump discharge.

+Is there a bad season to install a French drain in Myrtle Beach?

Not from a temperature point of view. NOAA's 1991-2020 normals show no month with a freezing-level overnight low or a 90°F-plus average high, so timing is mostly about contractor availability and rain.

French drain near Myrtle Beach

French drain: all pricesFrench drain in South CarolinaAll projects in Myrtle BeachSouth Carolina cost hub

Where these numbers come from

Base prices are national ranges from the sources below. We scale labor by local BLS wages, materials by BEA goods prices and permits by the BEA all-items price level. Full method on the methodology page.

Note on derived figures: Materials = 48% of the installed price, from Cost to Renovate's mid-range 'Outdoor Living' category split (44% labor, 48% materials). It is a category average, not a French-drain figure, so the materials line here is a rough one.